## The story

A $311 million line. Two ends. No named data center.

The track is settled.

The Alaska Railroad's board approved the $311 million line, 32 miles from Port MacKenzie to the main line near Houston. The Legislature backed it 58-1.

$249 million federal. $62 million local.

AIDEA's share is $33 million in the Alaska Beacon's count and up to $34 million in the board's June resolution. The Mat-Su Borough adds cash, land and gravel. The railroad pays additional costs from savings.

Land for projects nobody has named.

DNR cut AIDEA's conveyance near Houston from 19,500 acres to about 6,800. AIDEA says uses could include an industrial hub or data centers. It says it hasn't identified a specific project.

Proposed in 1992, before there was a port.

Announced. Not named.

The Alaska Beacon reports a coal-fired computing data center has announced plans at the port. It doesn't name the developer. Terra Energy, a coal plant developer in a two-year marketing effort with the borough, isn't building one, Alaska Business reported in April.

AIDEA's match goes back on the table.

AIDEA approved up to $34 million in June. Its board takes the match back up Friday, after the governor-elect asked AIDEA to freeze added spending until he takes office December 7th.

The cost has a source.

The borough calls Point MacKenzie and parts of West Susitna more appropriate locations. Reconsideration requests on the Houston transfer are due November 30th.

What should a $311 million public line be built to carry?

## What we verified

- AIDEA's Amended Resolution G26-07 approved the use of up to $34 million from the AIDEA Revolving Fund as a partial match for the Alaska Railroad's CRISI grant. [Alaska Industrial Development and Export Authority (signed board minutes)](https://www.aidea.org/Portals/0/Meeting%20Docs/2026BoardMeetings/082626/Signed_AIDEA_Meeting_Minutes_17_JUNE_2026_08262026.pdf), primary document, 2026-08-26.
- AIDEA's board passed the Port MacKenzie resolution unanimously on a roll call on June 17th. [Alaska Industrial Development and Export Authority (signed board minutes)](https://www.aidea.org/Portals/0/Meeting%20Docs/2026BoardMeetings/082626/Signed_AIDEA_Meeting_Minutes_17_JUNE_2026_08262026.pdf), primary document, 2026-08-26.
- At the June 17th AIDEA meeting O'Leary said the grant required a 20 percent match of as much as $60 million. [Alaska Industrial Development and Export Authority (signed board minutes)](https://www.aidea.org/Portals/0/Meeting%20Docs/2026BoardMeetings/082626/Signed_AIDEA_Meeting_Minutes_17_JUNE_2026_08262026.pdf), primary document, 2026-08-26.
- O'Leary attended the June 17th AIDEA meeting in person and spoke in support of the Port MacKenzie rail extension item. [Alaska Industrial Development and Export Authority (signed board minutes)](https://www.aidea.org/Portals/0/Meeting%20Docs/2026BoardMeetings/082626/Signed_AIDEA_Meeting_Minutes_17_JUNE_2026_08262026.pdf), primary document, 2026-08-26.
- Ruaro told the board that AIDEA is not the only match provider, with the Mat-Su Borough and the railroad also contributing. [Alaska Industrial Development and Export Authority (signed board minutes)](https://www.aidea.org/Portals/0/Meeting%20Docs/2026BoardMeetings/082626/Signed_AIDEA_Meeting_Minutes_17_JUNE_2026_08262026.pdf), primary document, 2026-08-26.
- In June O'Leary put the project's outlay at approximately $300 million. [Alaska Industrial Development and Export Authority (signed board minutes)](https://www.aidea.org/Portals/0/Meeting%20Docs/2026BoardMeetings/082626/Signed_AIDEA_Meeting_Minutes_17_JUNE_2026_08262026.pdf), primary document, 2026-08-26.
- AIDEA's November 24th board meeting is in recess and will resume at 10 a.m. on Friday, November 27th. [Alaska Industrial Development and Export Authority](https://www.aidea.org/About/Board-Members/Board-Meeting-Schedule), primary document, 2026-11-25.
- AIDEA's schedule lists the November 24th meeting as a continuation of its November 19th board meeting. [Alaska Industrial Development and Export Authority](https://www.aidea.org/About/Board-Members/Board-Meeting-Schedule), primary document, 2026-11-25.
- AIDEA's next regularly scheduled board meeting is Friday, December 4th. [Alaska Industrial Development and Export Authority (board agenda)](https://www.aidea.org/Portals/0/Meeting%20Docs/2026BoardMeetings/111926/Updated%2011.19.26%20AIDEA-Agenda%20Public%20Linked%20Agenda%2011192026.pdf), primary document, 2026-11-19.
- The agenda for AIDEA's November 19th board meeting listed an Amended Second Resolution G26-07 on Port Mackenzie Infrastructure and Real Estate. [Alaska Industrial Development and Export Authority (board agenda)](https://www.aidea.org/Portals/0/Meeting%20Docs/2026BoardMeetings/111926/Updated%2011.19.26%20AIDEA-Agenda%20Public%20Linked%20Agenda%2011192026.pdf), primary document, 2026-11-19.
- The Department of Energy selected Terra Energy Center Corporation's planned 1,250 MW coal plant with carbon capture in the Mat-Su Borough for engineering and design funding. [U.S. Department of Energy](https://www.energy.gov/hgeo/project-selections-broad-agency-announcement-de-foa-0003605-restoring-reliability-coal-0), primary document, 2026-10-05.
- DOE's selection lists $89 million in federal funding for the Terra Energy Center project. [U.S. Department of Energy](https://www.energy.gov/hgeo/project-selections-broad-agency-announcement-de-foa-0003605-restoring-reliability-coal-0), primary document, 2026-10-05.
- NMFS published a proposed rule redefining pelagic trawl gear off Alaska in the Federal Register on November 16th. [Federal Register (National Marine Fisheries Service, NOAA)](https://www.federalregister.gov/documents/full_text/text/2026/11/16/2026-23251.txt), primary document, 2026-11-16.
- Comments on the pelagic trawl proposed rule are due by December 16th. [Federal Register (National Marine Fisheries Service, NOAA)](https://www.federalregister.gov/documents/full_text/text/2026/11/16/2026-23251.txt), primary document, 2026-11-16.
- The proposed rule would allow sensors and electronic instruments designed to adjust the gear, exclude bycatch or minimize contact with the seafloor. [Federal Register (National Marine Fisheries Service, NOAA)](https://www.federalregister.gov/documents/full_text/text/2026/11/16/2026-23251.txt), primary document, 2026-11-16.
- NMFS says live feed cameras that let operators see catch entering the net in real time have been widely adopted. [Federal Register (National Marine Fisheries Service, NOAA)](https://www.federalregister.gov/documents/full_text/text/2026/11/16/2026-23251.txt), primary document, 2026-11-16.
- From 2019 to 2024, 147 vessels used pelagic trawl gear off Alaska. [Federal Register (National Marine Fisheries Service, NOAA)](https://www.federalregister.gov/documents/full_text/text/2026/11/16/2026-23251.txt), primary document, 2026-11-16.
- The Alaska Railroad's board of directors gave final approval to the $311 million Port MacKenzie rail line in the week of November 16th. [Alaska Beacon (James Brooks), republished by Mat-Su Sentinel](https://www.matsusentinel.com/port-mackenzie-rail-construction-could-come-as-soon-as-summer-alaska-railroad-ceo-says/), report, 2026-11-20.
- The 32-mile line will connect Port MacKenzie to the railroad's main line near Houston. [Alaska Beacon (James Brooks), republished by Mat-Su Sentinel](https://www.matsusentinel.com/port-mackenzie-rail-construction-could-come-as-soon-as-summer-alaska-railroad-ceo-says/), report, 2026-11-20.
- A $249 million federal grant will fund most of the rail extension. [Alaska Beacon (James Brooks), republished by Mat-Su Sentinel](https://www.matsusentinel.com/port-mackenzie-rail-construction-could-come-as-soon-as-summer-alaska-railroad-ceo-says/), report, 2026-11-20.
- AIDEA is expected to provide $33 million in matching funds to unlock the federal grant. [Alaska Beacon (James Brooks), republished by Mat-Su Sentinel](https://www.matsusentinel.com/port-mackenzie-rail-construction-could-come-as-soon-as-summer-alaska-railroad-ceo-says/), report, 2026-11-20.
- The Mat-Su Borough will provide cash, land and gravel to fulfill the remainder of the required match. [Alaska Beacon (James Brooks), republished by Mat-Su Sentinel](https://www.matsusentinel.com/port-mackenzie-rail-construction-could-come-as-soon-as-summer-alaska-railroad-ceo-says/), report, 2026-11-20.
- The Alaska Railroad will pay additional project costs from its savings. [Alaska Beacon (James Brooks), republished by Mat-Su Sentinel](https://www.matsusentinel.com/port-mackenzie-rail-construction-could-come-as-soon-as-summer-alaska-railroad-ceo-says/), report, 2026-11-20.
- Alaska Railroad CEO Bill O'Leary said the goal is to break ground this summer, depending on how fast the grantor agency moves. [Alaska Beacon (James Brooks), republished by Mat-Su Sentinel](https://www.matsusentinel.com/port-mackenzie-rail-construction-could-come-as-soon-as-summer-alaska-railroad-ceo-says/), report, 2026-11-20.
- O'Leary said the railroad expects to know the grantor agency's stance on its timeline in about a month to six weeks. [Alaska Beacon (James Brooks), republished by Mat-Su Sentinel](https://www.matsusentinel.com/port-mackenzie-rail-construction-could-come-as-soon-as-summer-alaska-railroad-ceo-says/), report, 2026-11-20.
- The rail spur was proposed as far back as 1992, before Port MacKenzie was built. [Alaska Beacon (James Brooks), republished by Mat-Su Sentinel](https://www.matsusentinel.com/port-mackenzie-rail-construction-could-come-as-soon-as-summer-alaska-railroad-ceo-says/), report, 2026-11-20.
- The project began moving forward in 2002, when proponents started clearing a 30-foot-wide right-of-way. [Alaska Beacon (James Brooks), republished by Mat-Su Sentinel](https://www.matsusentinel.com/port-mackenzie-rail-construction-could-come-as-soon-as-summer-alaska-railroad-ceo-says/), report, 2026-11-20.
- The project was poised to move forward in 2007, but local opposition and a lack of funding stopped it. [Alaska Beacon (James Brooks), republished by Mat-Su Sentinel](https://www.matsusentinel.com/port-mackenzie-rail-construction-could-come-as-soon-as-summer-alaska-railroad-ceo-says/), report, 2026-11-20.
- The Alaska Legislature voted 58-1 in favor of a resolution backing the rail line. [Alaska Beacon (James Brooks), republished by Mat-Su Sentinel](https://www.matsusentinel.com/port-mackenzie-rail-construction-could-come-as-soon-as-summer-alaska-railroad-ceo-says/), report, 2026-11-20.
- According to the Alaska Beacon, the developers of an antimony mine and of a coal-fired computing data center have announced construction projects at the port in anticipation of the rail line. [Alaska Beacon (James Brooks), republished by Mat-Su Sentinel](https://www.matsusentinel.com/port-mackenzie-rail-construction-could-come-as-soon-as-summer-alaska-railroad-ceo-says/), report, 2026-11-20.
- AIDEA voted to approve its share of the match on June 17th. [Alaska Beacon (James Brooks), republished by Mat-Su Sentinel](https://www.matsusentinel.com/port-mackenzie-rail-construction-could-come-as-soon-as-summer-alaska-railroad-ceo-says/), report, 2026-11-20.
- AIDEA's board was scheduled to discuss the rail match again at a meeting on Tuesday, November 24th. [Alaska Beacon (James Brooks), republished by Mat-Su Sentinel](https://www.matsusentinel.com/port-mackenzie-rail-construction-could-come-as-soon-as-summer-alaska-railroad-ceo-says/), report, 2026-11-20.
- Gov.-elect Jonathan Kreiss-Tomkins has asked AIDEA to pause spending actions until he takes office in early December. [Alaska Beacon (James Brooks), republished by Mat-Su Sentinel](https://www.matsusentinel.com/port-mackenzie-rail-construction-could-come-as-soon-as-summer-alaska-railroad-ceo-says/), report, 2026-11-20.
- O'Leary said he doesn't think the incoming governor will oppose the railroad project. [Alaska Beacon (James Brooks), republished by Mat-Su Sentinel](https://www.matsusentinel.com/port-mackenzie-rail-construction-could-come-as-soon-as-summer-alaska-railroad-ceo-says/), report, 2026-11-20.
- The grant was paid for with money approved for a rail program under the bipartisan infrastructure law. [Alaska Beacon (James Brooks), republished by Mat-Su Sentinel](https://www.matsusentinel.com/port-mackenzie-rail-construction-could-come-as-soon-as-summer-alaska-railroad-ceo-says/), report, 2026-11-20.
- Sen. Dan Sullivan called the grant a major win for the Mat-Su Borough and the state. [Alaska Beacon (James Brooks), republished by Mat-Su Sentinel](https://www.matsusentinel.com/port-mackenzie-rail-construction-could-come-as-soon-as-summer-alaska-railroad-ceo-says/), report, 2026-11-20.
- Sen. Lisa Murkowski said good things happen in Alaska when infrastructure is funded at the federal level. [Alaska Beacon (James Brooks), republished by Mat-Su Sentinel](https://www.matsusentinel.com/port-mackenzie-rail-construction-could-come-as-soon-as-summer-alaska-railroad-ceo-says/), report, 2026-11-20.
- The state spent $180 million on the rail line between 2005 and 2017. [Alaska Public Media (Tim Bradner, Mat-Su Sentinel)](https://alaskapublic.org/news/economy/2026-10-20/stalled-port-mackenzie-rail-project-to-get-new-life-with-249m-federal-grant), report, 2026-10-20.
- The federal funding requires a $62 million local cost share. [Alaska Public Media (Tim Bradner, Mat-Su Sentinel)](https://alaskapublic.org/news/economy/2026-10-20/stalled-port-mackenzie-rail-project-to-get-new-life-with-249m-federal-grant), report, 2026-10-20.
- Alaska Public Media reported in October that AIDEA agreed to cover about half of the $62 million local share. [Alaska Public Media (Tim Bradner, Mat-Su Sentinel)](https://alaskapublic.org/news/economy/2026-10-20/stalled-port-mackenzie-rail-project-to-get-new-life-with-249m-federal-grant), report, 2026-10-20.
- The Mat-Su Borough's letter asking the state to reconsider the Houston land transfer was signed by Borough Manager Mike Brown and Mayor Edna DeVries. [Alaska Public Media (Amy Bushatz, Mat-Su Sentinel)](https://alaskapublic.org/news/economy/2026-11-17/mat-su-borough-asks-state-to-reverse-aidea-land-transfer-consider-point-mackenzie-instead), report, 2026-11-17.
- The borough letter says Point Mackenzie and portions of West Susitna offer more appropriate locations for the proposed uses. [Alaska Public Media (Amy Bushatz, Mat-Su Sentinel)](https://alaskapublic.org/news/economy/2026-11-17/mat-su-borough-asks-state-to-reverse-aidea-land-transfer-consider-point-mackenzie-instead), report, 2026-11-17.
- The borough letter notes that $180 million has been spent on a rail bed slated to receive about $249 million in new federal funding. [Alaska Public Media (Amy Bushatz, Mat-Su Sentinel)](https://alaskapublic.org/news/economy/2026-11-17/mat-su-borough-asks-state-to-reverse-aidea-land-transfer-consider-point-mackenzie-instead), report, 2026-11-17.
- DNR approved a transfer of about 6,800 acres near Houston to AIDEA, scaled back from an initial proposal of almost 20,000 acres. [Alaska Public Media (Amy Bushatz, Mat-Su Sentinel)](https://alaskapublic.org/news/economy/2026-11-17/mat-su-borough-asks-state-to-reverse-aidea-land-transfer-consider-point-mackenzie-instead), report, 2026-11-17.
- DNR received more than 2,300 public comments on the no-cost transfer, almost all of them opposed. [Alaska Public Media (Amy Bushatz, Mat-Su Sentinel)](https://alaskapublic.org/news/economy/2026-11-17/mat-su-borough-asks-state-to-reverse-aidea-land-transfer-consider-point-mackenzie-instead), report, 2026-11-17.
- Anyone who commented on the transfer can request reconsideration by November 30th. [Alaska Public Media (Amy Bushatz, Mat-Su Sentinel)](https://alaskapublic.org/news/economy/2026-11-17/mat-su-borough-asks-state-to-reverse-aidea-land-transfer-consider-point-mackenzie-instead), report, 2026-11-17.
- DNR has 30 days to respond to reconsideration requests. [Alaska Public Media (Amy Bushatz, Mat-Su Sentinel)](https://alaskapublic.org/news/economy/2026-11-17/mat-su-borough-asks-state-to-reverse-aidea-land-transfer-consider-point-mackenzie-instead), report, 2026-11-17.
- The Houston land transfer is the subject of a pending lawsuit. [Alaska Public Media (Amy Bushatz, Mat-Su Sentinel)](https://alaskapublic.org/news/economy/2026-11-17/mat-su-borough-asks-state-to-reverse-aidea-land-transfer-consider-point-mackenzie-instead), report, 2026-11-17.
- Kreiss-Tomkins, who is sworn in on December 7th, has said he would completely reassess everything AIDEA is looking at. [Alaska Public Media (Amy Bushatz, Mat-Su Sentinel)](https://alaskapublic.org/news/economy/2026-11-17/mat-su-borough-asks-state-to-reverse-aidea-land-transfer-consider-point-mackenzie-instead), report, 2026-11-17.
- An AIDEA proposal says the Houston land could be used for projects not yet identified, which could include an industrial hub or data centers. [Alaska Public Media (Amy Bushatz, Mat-Su Sentinel)](https://alaskapublic.org/news/economy/2026-11-17/mat-su-borough-asks-state-to-reverse-aidea-land-transfer-consider-point-mackenzie-instead), report, 2026-11-17.
- In July AIDEA said the Houston land could be used for a logistics hub, advanced manufacturing and scalable data centers. [The Alaska Current (James Brooks, Alaska Beacon)](https://thealaskacurrent.com/2026/11/10/alaska-aidea-data-centers/), report, 2026-11-10.
- AIDEA said it has not identified a specific project or projects for the Houston land. [The Alaska Current (James Brooks, Alaska Beacon)](https://thealaskacurrent.com/2026/11/10/alaska-aidea-data-centers/), report, 2026-11-10.
- DNR reduced the conveyance to AIDEA from 19,500 acres to approximately 6,800 acres. [The Alaska Current (James Brooks, Alaska Beacon)](https://thealaskacurrent.com/2026/11/10/alaska-aidea-data-centers/), report, 2026-11-10.
- Terra Energy Center Corporation is a branch of Flatlands Energy, a subsidiary of Alberta-based Alaska Asia Clean Energy Corporation. [Alaska Business (Rindi White)](https://www.akbizmag.com/featured/mat-su-borough-partners-with-coal-plant-developer-seeking-data-center-options/), report, 2026-04-15.
- Terra Energy Center Corporation holds a land-use permit on about 1,000 acres near Lake Lorraine at Point MacKenzie. [Alaska Business (Rindi White)](https://www.akbizmag.com/featured/mat-su-borough-partners-with-coal-plant-developer-seeking-data-center-options/), report, 2026-04-15.
- Alaska Business reported in April that Terra Energy Center Corporation isn't building a data center itself. [Alaska Business (Rindi White)](https://www.akbizmag.com/featured/mat-su-borough-partners-with-coal-plant-developer-seeking-data-center-options/), report, 2026-04-15.
- By overriding a mayoral veto in March, the Mat-Su Borough Assembly authorized staff to work with a company pitching a coal-fired power plant near Skwentna to serve large consumers such as a data center. [Alaska Business (Rindi White)](https://www.akbizmag.com/featured/mat-su-borough-partners-with-coal-plant-developer-seeking-data-center-options/), report, 2026-04-15.
- The Assembly let Terra Energy Center Corporation start a two-year joint international marketing effort with borough staff. [Alaska Business (Rindi White)](https://www.akbizmag.com/featured/mat-su-borough-partners-with-coal-plant-developer-seeking-data-center-options/), report, 2026-04-15.
- Kreiss-Tomkins asked AIDEA to freeze plans for additional spending before he takes office on December 7th. [Alaska Public Media (James Brooks, Alaska Beacon)](https://alaskapublic.org/news/politics/2026-11-20/gov-elect-kreiss-tomkins-calls-for-pause-on-additional-aidea-action-after-multimillion-dollar-moves), report, 2026-11-20.
- The governor-elect's statement cited $200 million in AIDEA financial commitments since October. [Alaska Public Media (James Brooks, Alaska Beacon)](https://alaskapublic.org/news/politics/2026-11-20/gov-elect-kreiss-tomkins-calls-for-pause-on-additional-aidea-action-after-multimillion-dollar-moves), report, 2026-11-20.