NOVEMBER 26TH · 9 SLIDES

Fairbanks' data center pause, its fixed end and open start

In the Mona Lisa Drexler Assembly Chambers on November 10th, all eleven Fairbanks planning commissioners backed a data center pause.

The deck

SWIPE, SCROLL OR CLICK A SLIDE TO GO FULLSCREEN · 9 SLIDES

01 / 09
01 / 09

The story

Their version ends June 30th, 2028 instead of December 31st, 2027. The study went from six months to ten. Four of the six added months go to the study.

The start waits on the Assembly. The mayor says a vote is likely January 14th, 2027. Adoption that day leaves about seven and a half months to write rules. Every week of delay comes out of that.

All five edits appear by line number with where the added months went and the 40,000 square foot line, then the mayor's belief that a purely government data center falls outside the pause.

What lands on the Assembly's desk first, finished rules or a request to extend the pause?

What we verified

52 CLAIMS, EACH RE-FETCHED FROM ITS SOURCE BEFORE THIS DECK SHIPPED

  1. The Fairbanks North Star Borough Planning Commission voted 11-0 to recommend that the Borough Assembly adopt Ordinance 2026-42 with amendments.

  2. Ordinance 2026-42 establishes a temporary moratorium on land use permits for large scale data centers and was sponsored by Mayor Hopkins.

  3. The commission amended line 60 of the ordinance to add the word gross before floor area.

  4. The commission amended line 60 to replace 50,000 with 40,000 in the floor area trigger.

  5. The commission amended line 33 to insert the words and impacting water quality after generating noise.

  6. The commission amended line 65 to move the moratorium end date from December 31st, 2027 to June 30th, 2028.

  7. The commission amended line 73 to change the study deadline from six months to ten months.

  8. Eleven Planning Commission members are listed as present at the November 10th meeting, and none were absent.

  9. Kevin McKinley is listed as chair of the Planning Commission.

  10. The action memorandum covers the Planning Commission meeting of November 10th.

  11. The action memorandum is dated November 13th and addressed to Mayor Grier Hopkins.

  12. The same night, the commission voted 11-0 to sponsor and recommend adoption of the 2026 FNSB Regional Comprehensive Plan.

  13. The commission attached 19 numbered amendments to its comprehensive plan recommendation, each adopted without objection.

  14. The memorandum says the next Planning Commission meeting is scheduled for December 15th.

  15. The borough's meeting calendar lists a Planning Commission meeting on December 15th with no agenda published yet.

  16. The borough's meeting calendar lists a Regular Assembly Meeting on December 17th, and its agenda had not been posted when checked.

  17. The November 10th Planning Commission meeting was set for 6 p.m. in the Mona Lisa Drexler Assembly Chambers at the Juanita Helms Administration Center.

  18. As referred, the ordinance defines a large-scale data center to include a facility with an aggregate peak electrical demand of five megawatts or greater.

  19. As referred, the ordinance's second trigger is a facility occupying more than 50,000 square feet of floor area devoted to data center operations.

  20. The ordinance's third trigger is onsite electrical generation facilities with a generating capacity of five megawatts or greater.

  21. The ordinance states that under present zoning large-scale data centers would be permitted only in the GU-1 and GU-5 General Use Districts.

  22. Section 2 says no land use permit applications for a large-scale data center shall be accepted, nor pending applications approved, while the moratorium is in effect.

  23. As referred, Section 3 keeps the moratorium in effect through December 31st, 2027 unless the Assembly ends or extends it sooner by ordinance.

  24. Section 4 directs the Department of Community Planning to study data center impacts on energy usage, air quality, water usage and water quality, and noise pollution.

  25. As referred, Section 4 required the department's report and recommendations within six months of the ordinance taking effect.

  26. Section 5 makes the ordinance effective at 5 p.m. on the first Borough business day after its adoption.

  27. The ordinance's first WHEREAS clause cites growing demand from artificial intelligence creating a need for physical infrastructure.

  28. The ordinance says the borough's Regional Comprehensive Plan was last updated in 2005.

  29. The ordinance says the Comprehensive Plan update is expected to be finalized in early 2027.

  30. The ordinance warns large data centers could consume a significant share of available electrical power, generate noise and degrade air quality.

  31. The ordinance header prints its referral to the Planning Commission as 10/22/2026.

  32. The staff report says the Assembly referred Ordinance 2026-42 to the Planning Commission on October 26th.

  33. Staff wrote that the state's marijuana licensing timeline took about 18 months from the 2014 vote to the first license, which acted as a de facto moratorium.

  34. Title 18 defines a large scale development to include a retail or wholesale building exceeding 55,000 square feet of gross floor area.

  35. Title 18 also defines a large scale development as an entertainment facility exceeding 40,000 square feet with seating for 800 people or more.

  36. Staff recommended two amendments, adding gross before floor area and changing 50,000 square feet to 40,000 square feet.

  37. The staff report says the borough zoning code has no definition for data center and does not list it as a permitted or conditional use in any zone.

  38. The staff report says the Community Planning Department has received inquiries about data centers potentially being developed in the community.

  39. The staff report says the Municipality of Anchorage has researched and passed data center regulations.

  40. KTUU reported, citing Mayor Hopkins, that an Assembly vote will likely take place on January 14th.

  41. Mayor Hopkins told KTUU that adoption is when the clock will start for the 18-month moratorium.

  42. KTUU reported the commission's changes as extending the mayor's proposed 12-month timeframe to 18.

  43. Mayor Hopkins told KTUU a data center that comes in purely for a government purpose would, he believes, not be subject to the moratorium.

  44. KTUU reported Hopkins is confident any proposed data centers outside the Eielson Air Force Base fence would be under borough jurisdiction.

  45. Hopkins told KTUU the scale of what happens in other cities before they can act is relatively terrifying.

  46. KTUU reported the Borough Assembly voted unanimously to send the ordinance to the Planning Commission.

  47. Waymo is testing its self-driving taxis in Fairbanks, KUAC reported on November 16th.

  48. A Waymo spokesman told KUAC by email that the tests will be performed with a specialist at the wheel.

  49. KUAC reported that Governor Mike Dunleavy announced the Waymo testing in a post on X.

  50. HB 217, which regulates autonomous vehicles, passed the Alaska House on April 30th with 39 yeas and one excused.

  51. On May 17th the Senate State Affairs Committee reported HB 217 with two do not pass and one do pass recommendations.

  52. HB 217 was referred to the Senate Rules Committee on May 17th, its last recorded action.

Beats

This article is on Alaska data centers · Alaska land and permitting for AI. Each beat page keeps every decision and every article on that subject in one place.