The Alaska AI Docket

Every AI infrastructure decision in Alaska, tracked daily. Who decides, when it lands, and whether the public gets a say. Sources on every item.

45
DECISIONS TRACKED
01
OPEN TO THE PUBLIC
NOV 30
NEXT DATE
Docket agentPUBLISHED RECORD / VERIFIED SENTENCES
TRY
NEAR

Model in training

The search writes from the published record and is checked against it line by line. If an answer missed something or read oddly, that is worth knowing.

George M Sullivan Generation Plant 2, 309.3 MW, natural gasBeluga, 300.4 MW, natural gasSouthcentral Power Project, 169.7 MW, natural gasEklutna Generation Station, 165 MW, natural gasNorth Pole, 145 MW, petroleumBradley Lake, 126 MW, hydroelectricSoldotna, 90.5 MW, natural gasSnettisham, 78 MW, hydroelectricHealy, 77.8 MW, coalNikiski Combined Cycle, 75.9 MW, natural gasHank Nikkels Plant 1, 62.4 MW, natural gasBernice Lake, 62.4 MW, natural gasLemon Creek, 57.5 MW, petroleumEklutna Hydro Project, 44.4 MW, hydroelectricBattery Energy Storage System, 40 MW, batteriesInternational Battery Substation (IBSS), 40 MW, batteriesFairbanks, 36.1 MW, petroleumUniversity of Alaska Fairbanks, 35.7 MW, coalTerror Lake Microgrid, 33.6 MW, hydroelectricAuke Bay, 28.3 MW, petroleumChena Power Plant, 25.7 MW, coalJarvis Street, 25.1 MW, petroleumEielson AFB Central Heat & Power Plant, 24.6 MW, coalEva Creek Wind, 24.6 MW, windIndustrial Plant, 23.5 MW, petroleumDelta Power, 23.1 MW, petroleumTNSG North Plant, 23.1 MW, natural gasS W Bailey, 23 MW, petroleumSwan Lake, 22.6 MW, hydroelectricTyee Lake Hydroelectric Facility, 22.6 MW, hydroelectricUtility Plants Section, 22.1 MW, coal 1235 decisions at University of Alaska System, Fairbanks456818791011122 decisions at Soldotna, Kenai Peninsula Borough132914151617193 decisions at Juneau202330213 decisions at Anchorage22262724252831
Transmission at 69 kV and up. The raw state layer is 93 percent local distribution from one utility, so it is cut at the transmission floor.Power plants of 20 MW and up. That is 31 of Alaska's 152 plants but 78 percent of its capacity. Circle area is nameplate megawatts.The Trans Alaska Pipeline System. Gas lines are left out, being 96 percent sub-kilometre distribution with nothing to sort them by.

Closing soon

The nearest deadlines and votes. A pulsing pin on the map means a public comment window is open right now.

The docket

Access reads OPEN when a formal public comment or testimony path exists today, INDIRECT when an elected or member-accountable body decides, CLOSED when the evaluation is private.

01
CLOSED REGULATORY DOCKET next NOV 30

The Dixon Glacier diversion into Bradley Lake

DECIDES · FEDERAL ENERGY REGULATORY COMMISSION

The Alaska Energy Authority has asked FERC to amend the license for the Bradley Lake Hydroelectric Project, the largest in Alaska, so it can build a new dam diverting meltwater and surface runoff from the Dixon Glacier into Bradley Lake, raise the lake's normal maximum operating pool by about 16 feet, and install a 0.3 megawatt micro-hydro turbine in one of the dam's fishwater release valves. The application projects about 38 percent more average annual generation while installed capacity rises from 119.7 to 120.0 megawatts, because the gain comes from water rather than from turbines. AEA estimates construction at about $400 million and about three years of study and permitting followed by three years of construction. FERC accepting the application for filing is a procedural step and not an approval.

The comment window has closed. Anyone could file a comment, a motion to intervene or a protest in docket P-8221-124 until 5:00 p.m. Eastern on August 28th, 2026, which was 1:00 p.m. Alaska time, and that hour has passed. FERC now weighs the application and has published no decision date. The docket itself stays readable through FERC's eLibrary, so an Alaskan can follow what was filed without being able to add to it.
JUN 30Amendment application filed with FERC
JUL 23AEA board endorses a financing package for the expansion
AUG 3FERC notice published in the Federal Register
AUG 28Comments, motions to intervene and protests due, 5:00 p.m. Eastern
OCT 21Alaska Energy Authority holds a virtual industry day for the project
NOV 30Recommendations, terms and conditions, and fishway prescriptions due at FERC, 5:00 p.m. Eastern
JAN 14 2027Reply comments due at FERC, 5:00 p.m. Eastern
2026-11-27 · A Federal Register search today for Alaska documents published November 23rd to 27th, 38 in all, found nothing newer for Project No. 8221 than the October 6th notice. Recommendations remain due November 30th. Checked and unchanged.
02
INDIRECT DECISION vote NOV 30

Petersburg drafts a nine-month data center pause

DECIDES · PETERSBURG BOROUGH ASSEMBLY

On September 21st the Petersburg Borough Assembly tied 3 to 3 on starting the year-long data center moratorium the Planning Commission had asked for. On October 5th it voted unanimously to start two measures instead. Vice Mayor Jeigh Stanton Gregor's would have staff draft an ordinance pausing building permits for nine months for data centers that rely on on-site power generation or lack closed-loop cooling, while projects connecting to Petersburg's grid could still apply. Assembly Member Jeff Meucci's directs the borough manager to prepare amendments to the Title 19 zoning code to regulate data centers. Stanton Gregor's proposal aims to cover the whole borough except Kupreanof, where the earlier request covered only the municipal service area. In September, Utility Director Steve Harbour said selling that much power to one customer could significantly blunt how much electric rates will increase, and KFSK reported the borough utility has endorsed a small data center proposed by Mazzella Alaska LLC, with no megawatt figure given.

The Assembly has directed staff to draft the moratorium and zoning ordinances. KFSK reports both must return to the Assembly for consideration and public hearings before either can take effect, so residents can testify then. No hearing date has been set.
SEP 21Assembly ties 3 to 3 and the moratorium process does not start
OCT 5Assembly votes unanimously to have staff draft a nine-month moratorium and data center zoning rules
NOV 2Moratorium ordinance taken up at first reading; two more readings needed
NOV 16Assembly second reading of the data center moratorium ordinance, with public feedback
NOV 30Assembly third reading of the amended moratorium, with another public hearing, 6 p.m.
2026-11-27 · KFSK's newest report, read today, is still November 23rd, when the Assembly broadened the moratorium 5 to 2 and passed it 7 to 0 at second reading. The third reading and public hearing stay set for November 30th. Checked and unchanged.
03
INDIRECT DECISION next DEC 4

AIDEA's $75 million fiber investment subsidiary

DECIDES · AIDEA'S EXECUTIVE DIRECTOR, REPORTING EACH COMMITMENT TO THE AIDEA BOARD

AIDEA's board adopted Resolution G26-11 forming Northstar Fiber Development LLC, a wholly owned subsidiary that may invest up to $75 million in subsea and terrestrial fiber, landing stations and middle-mile networks, with Pacific connectivity first. The resolution picks no project, route or partner, and the executive director's power to commit funds under it expires December 31st, 2028.

The board adopted the resolution on October 21st. Any project the executive director approves under it is reported to the board at its next meeting, and the board's public meetings are the place to be heard. The next are listed for November 4th and December 4th.
OCT 21AIDEA board adopts Resolution G26-11
NOV 4Next AIDEA board meeting
NOV 19AIDEA board meeting
NOV 27Recessed AIDEA board meeting resumes, 10 a.m.
DEC 4AIDEA board meeting
DEC 31 2028Executive director's commitment authority under the resolution expires unless extended
2026-11-27 · AIDEA's board schedule, read today, says the November 24th continuation has adjourned. The November 27th session lists Amended Resolution G26-01 and Third Amended Resolution G26-07 and no fiber item. The next board meeting is December 4th at 10 a.m. Checked and unchanged.
04
OPEN TO YOU REGULATORY DOCKET by DEC 14

Alaska's bid to run its own carbon storage permits

DECIDES · ALASKA OIL AND GAS CONSERVATION COMMISSION APPLIES; THE U.S. ENVIRONMENTAL PROTECTION AGENCY DECIDES

The Alaska Oil and Gas Conservation Commission is applying to the Environmental Protection Agency for primary enforcement authority over Class VI wells, the wells used to inject carbon dioxide for permanent underground storage. If the application succeeds the state, not the federal government, would permit and police every carbon storage well in Alaska.

The Environmental Protection Agency is taking written comments on its proposed approval until December 14th, under docket EPA-HQ-OW-2026-4588, and will hold one virtual public hearing during that period. The state's own comment window closed at its May 14th hearing.
MAR 3Public meeting on adopting the state regulations
MAY 14State hearing, and the close of written and oral comment
OCT 29EPA proposes to approve Alaska's application and opens comment
DEC 14Comments on EPA's proposed approval due, docket EPA-HQ-OW-2026-4588
2026-11-24 · Searched the Federal Register today and found no correction or extension to EPA's October 29th proposed approval, document 2026-22085. Checked and unchanged.
06
INDIRECT GRANT next DEC 31

Alaska's second year of rural health transformation money

DECIDES · ALASKA DEPARTMENT OF HEALTH, UNDER A CMS COOPERATIVE AGREEMENT

CMS announced Year 2 Rural Health Transformation awards on November 9th, and Alaska's $272,653,149 is second only to Texas. Year 1 closed October 22nd with just under $249 million to 254 projects, seven of which buy an AI tool.

Fall applications closed October 28th. Alaskans reach the next round through an applying clinic, tribe, city or nonprofit.
OCT 22Year 1 closes, just under $249 million to 254 projects
OCT 28Year 2 fall applications due, 11:59 p.m.
NOV 9CMS announces Year 2 awards, Alaska second largest
DEC 31State says its public award dashboard is due by year end
2026-11-24 · The CMS Year 2 fact sheet, re-read today, still carries its November 9th date. Checked and unchanged.
07
INDIRECT DECISION next JAN 1 2027

The University of Alaska's AI policy

DECIDES · UNIVERSITY OF ALASKA BOARD OF REGENTS

A mandatory University of Alaska security standard has governed generative AI use across the system since January 2025, while the university's own guidance page, last updated March 11th, 2025, still says UA System regulations are currently under development. University leadership plans to submit a finalized draft artificial intelligence policy for approval at the November regents meeting, which KTOO reports would require all three campuses to develop AI plans for their communities.

There is no comment room on this one yet. The university says it plans listening sessions and online surveys this fall, and as of September 16th no session dates had been scheduled. The document binding users today is a security standard issued through the Office of Information Technology rather than anything the regents have voted on, and it has been in effect since January 2025. It applies to the UA System and all users of UA computing resources, and violations may subject employees to disciplinary action up to and including termination and students to disciplinary action including expulsion.
JAN 1 2025UA Generative AI Security Standard takes effect, dated January 2025 with no day given
MAR 11 2025The GenAI policies and guidelines page carries its last update stamp
SEP 16KTOO reports the Board of Regents reviewed a draft AI policy at a meeting at UAS
NOV 2Public testimony before the November regents meeting, 4 p.m. to 5 p.m.
NOV 4Regents committee meetings begin, 1 p.m.
NOV 5Board of Regents meets in Fairbanks, with AI guiding principles expected for consideration
NOV 6Board of Regents meeting continues in Fairbanks
NOV 6Regents delay the AI Engaged statement of intent to February
JAN 1 2027The security standard's own next scheduled review, January 2027 with no day given
2026-11-22 · The regents' policy and regulation index, read today, lists no AI policy or AI Engaged statement, adopted or pending. The final decision remains set for February. Checked and unchanged.
08
INDIRECT LEGISLATION decision JAN 14 2027

Fairbanks proposes its own pause on large data center permits

DECIDES · FAIRBANKS NORTH STAR BOROUGH ASSEMBLY, AFTER A PLANNING COMMISSION RECOMMENDATION

Mayor Grier Hopkins's Ordinance No. 2026-42 would accept no land use permit applications for large-scale data centers, and approve no pending ones, while the pause is in effect. As introduced it ran through December 31st, 2027 and defined large-scale as 5 MW or more of peak demand, more than 50,000 square feet of data center floor area, or 5 MW or more of onsite generation, with a study of energy, air, water and noise due within six months. On November 10th the Planning Commission recommended it to the Assembly 11-0 with amendments that count gross floor area, lower the floor area line to 40,000 square feet, add impacts on water quality to the findings, move the end date to June 30th, 2028 and give the study ten months. The Assembly makes the final decision.

The Planning Commission has made its recommendation. The elected Assembly holds its own public hearing before it adopts or rejects the ordinance, and that hearing is where a reader can still testify.
OCT 22Assembly refers it to the Planning Commission, recommendation due back in 90 days
OCT 27Planning Commission work session on the final Comprehensive Plan the moratorium waits for
NOV 10Planning Commission recommends adoption 11-0 with five amendments
JAN 14 2027Assembly vote on the ordinance expected, per the mayor
DEC 31 2027End date as introduced, which the Planning Commission moved to June 30th, 2028
JUN 30 2028Moratorium would end under the Planning Commission's amendment, unless the Assembly ends it sooner or extends it
2026-11-26 · Updated from the borough clerk's action memorandum for the November 10th meeting, dated November 13th. The Planning Commission recommended adoption 11-0, with all eleven members present, and amended the ordinance five ways. It adds gross before floor area and replaces 50,000 with 40,000 square feet, inserts impacting water quality among the harms in the findings, moves the end date from December 31st, 2027 to June 30th, 2028, and gives the study ten months instead of six. The same night the commission recommended the updated Regional Comprehensive Plan 11-0. The borough calendar lists a regular Assembly meeting on December 17th with no agenda posted yet. The mayor has said he expects the Assembly vote on January 14th.
09
INDIRECT LEGISLATION next JAN 19 2027

Fairbanks asks Juneau and Congress to pause data centers

DECIDES · ALASKA LEGISLATURE AND THE ALASKA CONGRESSIONAL DELEGATION

On August 27th, 2026 the Fairbanks North Star Borough Assembly adopted Resolution 2026-25, its list of 2027 state and federal legislative priorities, sponsored by the Assembly Committee of the Whole. The list carries 25 items, 21 state and 4 federal, and one item appears on both halves. It asks for a moratorium on the permitting, leasing or construction of new commercial data centers on state-owned or municipal lands in Alaska until standards exist for electrical demand, water consumption and shortages, environmental impacts, noise, air quality and land use pollution. Assemblymember Garrett Armstrong moved it onto the state list at an August 6th work session and an amendment replicated it onto the federal list. The request follows the Air Force offer of about 4,700 acres across twelve parcels at three Alaska installations, one of which, Eielson, is inside this borough. The adopted text reaches state and municipal land, not federal land, and KUAC reports Presiding Officer Scott Crass said by phone that federal land was intended too.

The borough has already voted, so the room that was open is closed. What the resolution does is hand the question to two bodies that have not acted on it. A reader who wants the moratorium considered asks a legislator to carry it when the Legislature convenes in January 2027, or asks the congressional delegation to take up the federal half. The resolution itself, its full text and the meeting record are public through the borough clerk.
AUG 6Armstrong moves the moratorium onto the state list at a Committee of the Whole work session
AUG 20Committee of the Whole takes up the priorities list
AUG 27Assembly adopts Resolution 2026-25
OCT 6Borough election for three Assembly seats whose candidates split on the moratorium request
OCT 22Assembly certifies the October 6th election and swears in the newly elected members
OCT 26Terms of the three newly elected Assembly members begin
JAN 19 2027The 35th Alaska Legislature convenes, the earliest the state half can be taken up
2026-11-26 · The borough's own pause, Ordinance No. 2026-42, was recommended 11-0 by the Planning Commission on November 10th and now awaits the Assembly, per the clerk's action memorandum. The state and federal requests in Resolution 2026-25 still wait on the 35th Legislature, which convenes in January. Checked and unchanged.
10
CLOSED FEDERAL LEASE Pending decision

Air Force land leases for AI data centers at JBER, Eielson and Clear

DECIDES · DEPARTMENT OF THE AIR FORCE, ENHANCED USE LEASE PROGRAM

The Air Force offered about 4,700 acres across 12 parcels at Joint Base Elmendorf-Richardson, Eielson AFB and Clear Space Force Station for privately financed AI data centers. Residents near the five Eielson-area parcels raised noise, permafrost and grid concerns, including one parcel less than a mile from North Pole Middle School.

Proposals closed in the spring and are evaluated privately. No public comment period exists and no award timeline has been announced. The solicitation record is public and carries no awardee.
APR 10Program announced
JUN 29Developer proposals due, 5 p.m. Eastern
JUL 14Solicitation record archived with no award posted
JUL 22U.S. House passes FY2027 NDAA carrying a data center lease restriction
JUL 23Bill introduced in the U.S. House to ban AI data centers on federal land
AUG 10Proposals due on a separate Eielson mixed-use lease covering 3,967 acres
SEP 15Sen. Murkowski says an insecure energy base keeps her from backing data centers at JBER and the Interior installations at this time
2026-11-27 · A Federal Register search today for Alaska documents published November 23rd to 27th, 38 in all, found no Air Force lease notice or award. Checked and unchanged.
11
INDIRECT UTILITY DECISION Pending decision

GVEA's $80 million turbine decision

DECIDES · GOLDEN VALLEY ELECTRIC ASSOCIATION BOARD OF DIRECTORS

Golden Valley Electric Association is weighing a 60 megawatt naphtha fueled turbine estimated at $80 million, to be installed beside an existing LM6000 at the co-op's North Pole Expansion plant. Its board voted on August 25th, 2026 to keep the purchase alive and to keep studying the risks and the alternatives.

A member-owned co-op board decides, in executive session. GVEA members reach it through board elections and member comment periods at regular meetings.
JUL 13Board weighs the purchase in executive session
AUG 25Board votes 4 to 3 in Delta Junction to move ahead on a possible purchase and to keep studying alternatives
OCT 12Golden Valley issues its first energy emergency alert, Level 2, about 15 MW of reserve
OCT 20Golden Valley issues a second energy emergency alert, Level 1, reserves below 38 MW
2026-11-26 · GVEA's website, read today, carries no turbine purchase item and lists its next board meeting on December 8th. Checked and unchanged.
12
INDIRECT REGULATORY DOCKET Pending decision

Enstar's Cook Inlet gas storage plan (Kenai Loop Pool)

DECIDES · REGULATORY COMMISSION OF ALASKA (PRUDENCY); ALASKA DNR (STORAGE LEASE AND TECHNICAL DETERMINATION)

The Regulatory Commission of Alaska denied Enstar's request for an advance determination that its proposed Cook Inlet gas storage project was prudent, in a 17-page order the Anchorage Daily News reported on July 10th, saying the utility lacked basic information. The $240 million plan would have bought the depleted Kenai Loop Pool from AIX Energy to hold 25 billion cubic feet of gas, close to half Enstar's annual demand, and Enstar suspended it after the order. The commission denied Enstar's petition for reconsideration 3 to 2 on August 21st, with a written order to follow. Enstar applied to the Alaska Oil and Gas Conservation Commission on September 17th to store gas in the Kenai Loop field, with a hearing tentatively set for November 12th. On October 13th the Division of Oil and Gas issued a preliminary written finding that a Kenai Loop storage lease to ENSTAR would best serve the state's interest, ahead of Hilcorp's competing application, and public comment on that finding runs until 5 p.m. on November 13th.

Written comments closed at 5 p.m. November 13th. The Division of Oil and Gas will issue a final written finding, and only people who submitted written comments can appeal it.
JUL 10RCA denies Enstar advance determination of prudency (ADN report); Enstar suspends the project
JUL 10DNR determination on Kenai Loop Pool storage capability and competing Enstar/Hilcorp leases still pending
AUG 21RCA denies reconsideration 3 to 2, with a written order to follow
AUG 22RCA acts on Enstar's petition for reconsideration, or the petition is denied automatically
SEP 17Enstar applies to the AOGCC to store gas in the Kenai Loop field
OCT 13Division of Oil and Gas issued a preliminary written finding favoring an ENSTAR storage lease, opening public comment
OCT 20Written requests for an AOGCC hearing on the Kenai Loop application due, 4:30 p.m.
NOV 12AOGCC hearing on the Kenai Loop application tentatively set, 10 a.m.
NOV 13Comments on the Kenai Loop storage lease preliminary finding due, 5 p.m.
2026-11-26 · The state's online notice for the Kenai Loop gas storage lease preliminary finding, read today, shows the comment period closed at 5 p.m. November 13th and no final finding posted. Checked and unchanged.
13
INDIRECT DECISION Watching

The AI ratepayer pledge, and which Alaska utilities have signed it

DECIDES · EACH ALASKA ELECTRIC UTILITY BOARD, INCLUDING THE RAILBELT COOPERATIVES

The White House Ratepayer Protection Pledge asks AI companies, utilities and data center developers to commit that new data center load pays for its own generation and delivery instead of shifting the cost onto households. USA TODAY and POWER both describe it as voluntary and non binding. Gov. Mike Dunleavy signed the governors addendum on July 23rd, 2026, one of 23 governors. The signatory list has grown from 281 when it was first read here on July 26th, 2026 to 324 on October 10th, and across that growth exactly one Alaska entity appears on it, Cordova Electric Cooperative, a 1,566 customer cooperative that is not connected by transmission line to any other community. No Railbelt utility has signed.

Alaska's electric cooperatives are governed by boards their own members elect, so a member can ask their board directly whether it intends to sign. A voluntary federal pledge has no public comment docket, which is why this room is indirect rather than open.
MAR 4Pledge first signed by seven AI companies at the White House
JUL 23Governors addendum signed, Dunleavy among 23 governors
JUL 26Signatory list read at 281, one Alaska entity on it
2026-11-26 · The White House pledge page, read today, lists 327 signatories and no Alaska utility among them. Checked and unchanged.
14
CLOSED PROCUREMENT Pending decision

Alaska's statewide speech-to-text contract

DECIDES · ALASKA DEPARTMENT OF ADMINISTRATION, OFFICE OF PROCUREMENT AND PROPERTY MANAGEMENT

Alaska is soliciting one statewide contract to convert speech, live or recorded, into written text for general, medical and legal records. The notice says every state governmental entity may use the resulting contract, naming the Legislative Branch, the Court System, the University of Alaska, boards and commissions, cities, boroughs, school districts and federally recognized tribes. The public notice does not use the terms artificial intelligence, machine learning or automated speech recognition.

A vendor solicitation, not a rulemaking, so no public comment period exists. Proposals closed August 28th and are evaluated privately. The notice and the named procurement officer are public, though the notice's own archive date has now passed. No award has been posted.
JUL 31Solicitation published on the state public notice system
AUG 28Vendor proposals due, 3:30 p.m. Alaska time
2026-11-26 · The state's online notice for RFP 2026-0200-0064, read today, still shows the August 28th due date and no award. Checked and unchanged.
15
CLOSED PROCUREMENT Watching

DMV asks vendors about automated compliance for commercial licenses

DECIDES · ALASKA DEPARTMENT OF ADMINISTRATION, DIVISION OF MOTOR VEHICLES

The Division of Motor Vehicles asked vendors for products, services, technical approaches and industry best practices related to automated compliance and data integration systems supporting the commercial driver's license program. The public notice does not use the terms artificial intelligence or machine learning.

A request for information gathers vendor input before any solicitation. There is no public comment path and no decision is made at this stage.
JUL 30Request for information published
AUG 20Vendor responses due, 2 p.m.
2026-11-26 · The state's online notice for RFI 02-101-27, read today, shows no change since its August 7th amendment. Checked and unchanged.
16
INDIRECT GRANT Pending decision

A national AI institute for Native communities, and the Alaska lane that closed with it

DECIDES · ADMINISTRATION FOR NATIVE AMERICANS, HHS ADMINISTRATION FOR CHILDREN AND FAMILIES

The Administration for Native Americans published its final Fiscal Year 2026 program policies on July 28th, 2026, standing up three funding opportunities and leaving out SEDS-AK, the Alaska-specific economic development program that ran alongside SEDS for decades. Two days later it posted the AI3 Action Institute, a single national award of up to $3,500,000 to build an artificial intelligence resource center for Native communities, with Alaska Native villages under ANCSA and nonprofit village consortia named as eligible applicants.

Only eligible applicants reached this one, and applications closed on August 27th, 2026, so no public path remains. An Alaskan reached it through a tribe, an ANCSA village or a Native nonprofit that filed in time. Applications are evaluated privately and no awardee has been named.
JUL 28Final Fiscal Year 2026 issuance published at 91 FR 47241, standing up EAGLE, the AI3 Action Institute and NCNTTA
JUL 28EAGLE posted, $24,000,000 across about 31 awards, applications due August 27
JUL 30AI3 Action Institute posted, one award, ceiling $3,500,000
AUG 27Applications close on both EAGLE and the AI3 Action Institute
SEP 26The posted opportunity is archived
2026-11-26 · The Grants.gov listing, read today, is still archived with no recipient named. Checked and unchanged.
17
CLOSED PROCUREMENT Pending decision

The Air Force nuclear microreactor at Eielson

DECIDES · DEPARTMENT OF THE AIR FORCE WITH DEFENSE LOGISTICS AGENCY ENERGY, AND THE NUCLEAR REGULATORY COMMISSION FOR THE LICENSE

The Air Force intends to award Oklo a 30 year fixed price power purchase agreement for a microreactor delivering up to 5 megawatts to Eielson Air Force Base outside Fairbanks. Oklo would build, own and operate it, and the contract is signed only after Oklo obtains a license from the Nuclear Regulatory Commission.

The comment window on the Air Force's preferred site near Spruce Lake closed on September 30th, and no extension was announced. The Air Force now weighs what it received and has published no date for a decision. The contract itself follows a Nuclear Regulatory Commission license.
JUN 11 2025Air Force announces a notice of intent to award to Oklo
SEP 20Public comment opens on the Air Force's preferred reactor site near Spruce Lake, which sits near wetlands
SEP 30Comments on the proposed microreactor site due to the Eielson Public Affairs Office
OCT 2Army Corps of Engineers posts a request for information on connecting the reactor to base utilities
OCT 16Responses to the Army Corps request for information due, 2 p.m. Alaska time
2026-11-25 · Searched the Federal Register today for Alaska documents published November 22nd to 25th, 29 in all, and found no Air Force, Oklo or reactor notice. Checked and unchanged.
18
CLOSED DECISION Watching

The executive order that lets big data centers skip the usual federal review

DECIDES · THE PRESIDENT, CARRIED OUT BY THE COUNCIL ON ENVIRONMENTAL QUALITY AND THE INTERIOR, ENERGY AND DEFENSE DEPARTMENTS

Executive Order 14318, Accelerating Federal Permitting of Data Center Infrastructure, directs federal agencies to speed approvals for data centers adding more than 100 megawatts of load or costing at least 500 million dollars. It tells agencies to find and create categorical exclusions under the National Environmental Policy Act, and directs Interior and Energy to offer federal sites while Defense may competitively lease military land.

An executive order takes no public comment. Its effect is to remove review steps that would otherwise have carried one, so the room this closes is the environmental review a project would have had.
JUL 23 2025Order signed
JUL 28 2025Published in the Federal Register
2026-11-25 · Searched the Federal Register today for Alaska documents published November 22nd to 25th, 29 in all, and found none citing Executive Order 14318. Checked and unchanged.
19
CLOSED GRANT Pending decision

An 89 million dollar federal grant for a coal plant in the Susitna watershed

DECIDES · U.S. DEPARTMENT OF ENERGY MADE THE SELECTION; THE PLANT ITSELF NEEDS STATE AND FEDERAL PERMITS NOBODY HAS APPLIED FOR YET

The Department of Energy selected Terra Energy Center Corporation of Anchorage, an affiliate of Flatlands Energy, for an 89 million dollar grant to study a 1,250 megawatt coal fired power plant west of Skwentna, with a 60 mile pipeline carrying its carbon dioxide to Beluga for injection into a depleted gas reservoir. The money funds a viability assessment rather than construction, and Terra must match it.

The grant selection carried no public comment period. Comment rooms open later, when the mine, the plant, the pipeline and the injection well each need their own permits.
JUN 4Federal grant selection announced
2026-11-25 · Re-read the Department of Energy's project selections page today. It still lists Terra Energy Center Corporation of Anchorage for engineering and design of a 1,250 MW coal plant with carbon capture in the Mat-Su Borough. Checked and unchanged.
20
INDIRECT DECISION Pending decision

The Kenai Peninsula school district's AI rulebook

DECIDES · KENAI PENINSULA BOROUGH SCHOOL DISTRICT BOARD OF EDUCATION

The Kenai Peninsula Borough School District is writing the rules for artificial intelligence in its 39 schools while the school year starts. Its Policy Review Committee took up AR 5131.9 Academic Honesty, a new administrative regulation the district says was brought forward in relation to the inclusion of AI, on August 3rd, 2026, with two competing drafts posted, one from Administration and one from board member Mica VanBuskirk. That same evening the full board took first readings on three more documents the district describes as revised for AI-related policy shifts, AR 5125 Student Records, BP 1114 Communication Using Electronic Media and BP 5131.9 Academic Honesty, plus AR 6161.4 Acceptable Use. The board adopted both academic honesty documents on September 14th, BP 5131.9 on a second reading and AR 5131.9 as a new administrative regulation, inside a single unanimous consent agenda motion. The rest of the package has no adoption recorded. The district told KBBI in July that it has spent 8,300 dollars to date on a three year MagicSchool subscription for students and staff, so the classroom AI tool was bought before the rulebook was finished. Upstream sits Alaska's Strategic Framework, Artificial Intelligence for K-12, issued by the Department of Education and Early Development, which means what Kenai adopts previews what other Alaska districts face.

An elected school board decides, and its regular meetings carry a public comment period. There is no formal comment window on these documents and no published date for a final vote, so an Alaskan reaches this one through a board member or from the podium at a meeting.
JUL 6AR 5131.9 first presented to the Policy Review Committee and postponed
AUG 3Committee takes up AR 5131.9 with two competing drafts, and the board takes first readings on four more documents that evening
AUG 19First student day of the 2026-27 year districtwide
SEP 14Board adopts BP 5131.9 on second reading and approves AR 5131.9 as a new administrative regulation, 9 to 0 on the consent agenda
2026-11-22 · The district's agenda listing for AR 5131.9, read today, still shows the August 3rd committee review and nothing newer. The board's September 14th adoption stands. Checked and unchanged.
21
CLOSED REGULATORY DOCKET Pending decision

DeepGreen's underwater data center in Cook Inlet

DECIDES · FEDERAL ENERGY REGULATORY COMMISSION

DeepGreen Cook Inlet SPV LLC, a Delaware company whose parent formed in January 2026, applied to FERC in February for a preliminary permit over an initial operational envelope of 1,650 acres of Cook Inlet seabed west of Nikiski, proposing a 100 megawatt data center of 66 hives of AI servers powered and cooled by approximately 330 to 350 tidal turbines in water 45 to 166 feet deep. A preliminary permit authorizes study rather than construction, for up to four years, and FERC's Northwest branch found the application incomplete in a June 18th letter.

The comment room has closed. Comments, motions to intervene and competing applications on Project No. P-15423-000 were due by 5:00 p.m. Eastern Time on November 2nd, 2026, which was 1:00 p.m. Alaska time. FERC now decides whether to grant DeepGreen Cook Inlet SPV, LLC up to four years of study and site priority. A preliminary permit is not authority to build, and any license application would open a new record.
FEB 11Preliminary permit application filed with FERC
JUN 18FERC's Northwest branch finds the application incomplete
JUN 26Application supplemented
AUG 19First Alaska reporting on the filing
SEP 4FERC accepts the application for filing and publishes notice in the Federal Register
SEP 14Kenai Peninsula Borough files a motion to intervene
SEP 20Alaska Energy Authority marine survey crews mobilise for the Cook Inlet PowerLink in the same inlet
SEP 21DeepGreen files a response with the commission
OCT 8Alaska Energy Authority moves to intervene, taking no position for or against the permit
OCT 13City of Kenai moves to intervene
OCT 22Cook Inlet PowerLink marine survey fieldwork ends
OCT 28Kenai Peninsula Borough mayor says the company has not contacted him
NOV 2Comments, motions to intervene and competing applications due, 5:00 p.m. Eastern
2026-11-27 · A Federal Register search today for Alaska documents published November 23rd to 27th, 38 in all, found nothing in P-15423. No order or permit decision has been published. Checked and unchanged.
22
CLOSED REGULATORY DOCKET Pending decision

The FCC asks whether AI should help run the Universal Service Fund

DECIDES · FEDERAL COMMUNICATIONS COMMISSION

The FCC published a notice on August 31st, 2026 seeking comment on how the Universal Service Fund is administered, and nine of its sentences name artificial intelligence. It asks whether AI tools used to review applications, audits and appeal review processes would reduce delays while maintaining accurate results, and whether the fund's administrator should expand use of AI in document review for audits and program compliance. One paragraph poses eight consecutive questions about AI. The Commission is asking rather than proposing, and every AI sentence in the notice is phrased as a question. The same notice seeks comment on cutting the administrator's board from 20 members to 13. Alaska is not named anywhere in it. Alaska's stake is in a companion notice published the same day, WC Docket No. 17-310, which reports that only 34 of 340 approved Telecom Program requests in Alaska in funding year 2025 relied on the Commission's preferred Methods 1 or 2, so the great majority of Alaska's rural health connectivity requests are justified the longer way. That is the paperwork an automated reviewer would read.

The comment room has closed. Initial comments closed on September 30th and reply comments on October 30th in WC Docket No. 26-173. The Commission now weighs the record, and an Alaska clinic, school district, library or carrier that did not file reaches the decision only through the delegation or an ex parte meeting under the Commission's rules.
AUG 6Adopted by the Commission
AUG 7Released
AUG 31Published in the Federal Register at 91 FR 55826
SEP 30Comments due, WC Docket No. 26-173
OCT 30Reply comments due, WC Docket No. 26-173
2026-11-27 · A Federal Register search today for Alaska documents published November 23rd to 27th, 38 in all, found nothing citing WC Docket No. 26-173. No order or further notice has been published. Checked and unchanged.
23
INDIRECT LEGISLATION Pending decision

The federal bill that would make a 100 megawatt customer pay for its own wires

DECIDES · U.S. HOUSE OF REPRESENTATIVES, THEN THE SENATE AND THE PRESIDENT, AND AFTER THAT EVERY STATE REGULATORY AUTHORITY INCLUDING THE REGULATORY COMMISSION OF ALASKA

H.R. 9340, the Ratepayer Protection Act, would add a standard to the Public Utility Regulatory Policies Act requiring that rates charged a large-load customer recover from that customer the full, incremental cost of any generation, transmission or distribution upgrade needed to serve it, and keep recovering it if the customer walks away. A large-load customer is a non-residential consumer with aggregate peak demand of 100 megawatts or more at one site or campus, running information technology infrastructure for data storage and computation, which is a data center described without the phrase. State regulators would get one year from enactment to begin considering it and two to decide. A state is excused if, before enactment, it implemented a comparable standard, conducted a proceeding on one, or its legislature voted on one. Alaska's Senate passed SB 250, a comparable cost-allocation bill, on May 16th, and the House never voted. Whether one chamber satisfies the words the State legislature has voted is unresolved, and it decides whether Alaska is already excused.

There is no comment room on a bill. The route is the congressional delegation, and after enactment it becomes a proceeding at the Regulatory Commission of Alaska, which is a room with a docket and a public record. The House passed the bill on September 16th and the Senate declined to take it up on September 30th, so it waits on the lame-duck session that opens November 9th.
JUL 21House Energy and Commerce advances the bill 52 to 0
SEP 10Reported to the House as H. Rept. 119-814 and placed on Union Calendar 713
SEP 16House passes the bill 417 to 3 on Roll No. 312
SEP 16Engrossed House text issued and the bill goes to the Senate
SEP 24Placed on the Senate legislative calendar as Calendar No. 684
SEP 28Motion to proceed made in the Senate and a cloture motion on it presented
SEP 30Senate rejects cloture on the motion to proceed, 57 to 43 with 60 needed
NOV 9The Senate returns for a five-week lame-duck session, per States Newsroom
2026-11-26 · GovInfo, read today, shows no version after the reported bill of September 10th, H. Rept. 119-814. Checked and unchanged.
24
CLOSED REGULATORY DOCKET Pending decision

Which grid equipment gets restricted, and the reason given is AI

DECIDES · U.S. DEPARTMENT OF ENERGY

A request for information implementing the August 26th emergency declaration on securing the United States bulk-power system. It asks which equipment and transactions should count as covered, naming grid-connected inverters, battery energy storage, universal power systems, generators and industrial control systems. The notice grounds the emergency in a finding that rapid growth of advanced manufacturing, data centers, artificial intelligence and defense production has increased the nation's dependence on abundant, reliable electricity. Alaska's Railbelt and rural utilities are mid-buildout on the inverter and storage categories listed, so a restriction reprices projects already in planning.

The written response period under docket DOE-HQ-2026-1123 closed on October 9th. The department has not said when it will act on the responses.
AUG 26Emergency declaration on the bulk-power system
SEP 9Request for information published
SEP 16Public webinar, 3 to 4 p.m. Eastern
OCT 9Written responses accepted on or before this date
2026-11-25 · Searched the Federal Register today for Alaska documents published November 22nd to 25th, 29 in all, and found no Energy Department document on the bulk-power system. Checked and unchanged.
25
CLOSED REGULATORY DOCKET Pending decision

Renting the highway shoulder to power and fiber, with data centers named as the draw

DECIDES · U.S. DEPARTMENT OF TRANSPORTATION, BUILD AMERICA BUREAU

A request for information launching America's Great Corridors of Commerce, a voluntary program letting highway and rail right-of-way owners raise revenue by colocating utility infrastructure in their corridors through public-private partnerships. Transmission, fiber, rural broadband and water pipelines are all named. One stated aim is to incentivize data centers, manufacturing facilities and distribution hubs to locate close to the corridors. Alaska has four long corridors and a railroad, and every large compute proposal in the state is shaped around one of them, yet the notice does not mention Alaska and frames the program around multi-state corridors, a shape no Alaskan right-of-way has.

The written comment period under docket DOT-OST-2026-3269 closed on October 2nd. The notice says late comments will be considered to the extent practicable, so a filing at regulations.gov is still possible, though a reading is no longer assured.
SEP 11Request for information published
OCT 2Written comments due
2026-11-27 · A Federal Register search today for Alaska documents published November 23rd to 27th, 38 in all, found no Department of Transportation corridors notice. Checked and unchanged.
26
INDIRECT DECISION Watching

North Slope Power, the borough's gas plant for AI data centers

DECIDES · NORTH SLOPE BOROUGH MAYOR AND ASSEMBLY

The North Slope Borough and Twenty First Century Utilities are developing North Slope Power, a gas-fired plant near Prudhoe Bay planned at 3 gigawatts in its first phase and meant to scale to 10, to deliver electricity to colocated AI data centers. As reported by the Alaska Current, the borough has funded a $1.2 million no-bid feasibility contract and committed another $5 million in public funds.

The borough commits money to North Slope Power by Assembly resolution and mayoral contract, so the elected borough government is the path in. The deal's financial structure has not been made public.
2026-11-24 · A search of The Alaska Current today found no report on the borough's plant newer than its October 3rd story. Checked and unchanged.
27
CLOSED GRANT Pending decision

A second power line between Southcentral and the Interior, Beluga to Healy

DECIDES · U.S. DEPARTMENT OF ENERGY, WITH THE ALASKA ENERGY AUTHORITY

On October 5th the Department of Energy announced its intent to put up to $150 million of Defense Production Act funding into the Alaska Energy Authority's Beluga-Healy Transmission Project, a second high-voltage connection between Southcentral and Interior Alaska. DOE counts on $268 million in non-federal funding for a preliminary estimate of about $418 million, and about 223 miles of new line. The Railbelt now relies on a single corridor, AEA's 170-mile Alaska Intertie between Willow and Healy, built in the mid-1980s. Energy Secretary Chris Wright tied the award to the military expansion under way in Alaska and to mining. The release does not mention data centers, though the Air Force has offered about 4,700 acres at JBER, Eielson and Clear for them.

The Energy Department chose this project under the Defense Production Act, and none of the announcements names a public comment period or a hearing. The Alaska Energy Authority, which proposed the line, now has to find the rest of the money.
AUG 28The Alaska Energy Authority presents Beluga to Healy to the Energy Secretary as a project under consideration
OCT 5Energy Department announces up to $150 million in Defense Production Act funding
2026-11-27 · Re-read the Department of Energy's October 5th release today. It still announces an intent to deploy up to $150 million in Defense Production Act funding beside $268 million in non-federal funding for about 223 miles of line, and reports no signed agreement. Checked and unchanged.
28
INDIRECT DECISION Pending decision

NOAA's 2027 fisheries monitoring plan includes an AI video project

DECIDES · NOAA FISHERIES, NATIONAL MARINE FISHERIES SERVICE

NOAA's draft 2027 plan assigns observers and electronic monitoring to Alaska groundfish and halibut fisheries, using a preliminary $5.45 million partial-coverage budget. It lists a project to scale AI tools for electronic-monitoring video analysis among work it intends to support in 2027, pending staff availability, not a funded deployment commitment.

NMFS consults the North Pacific Fishery Management Council and considers public input through its annual review. The Council does not formally approve the plan; final deployment is at NMFS's discretion. The draft gives nmfs.alaska.adp@noaa.gov for questions, concerns and 2027 monitoring needs.
NOV 6NOAA posts the draft 2027 annual deployment plan
2026-11-24 · The NOAA resource page, read today, still carries the November 6th draft and was last updated that day. No final plan is posted. Checked and unchanged.
29
INDIRECT STATE LAND LEASE Pending decision

Alaska LNG right-of-way lease conversion

DECIDES · ALASKA DNR COMMISSIONER

DNR proposes converting Alaska LNG's conditional right-of-way leases, ADL 421296 and 421297, into full leases. Per DNR, that grants no permission to build. Seven conditions remain later requirements.

Written comments closed at 5 p.m. on November 25th. The DNR Commissioner decides next, and DNR has published no date for that decision.
OCT 23Proposed decision issued
NOV 23Online hearing
NOV 24Anchorage hearing
NOV 25Written comments due, 5 p.m.
2026-11-25 · Written comments closed at 5 p.m. today, the deadline DNR set in its proposed decision. The Commissioner now weighs a final decision, and DNR has published no date for it.
30
INDIRECT LEGISLATION Pending decision

The Senate energy bill that names Alaska once, with an RCA approval step

DECIDES · U.S. HOUSE OF REPRESENTATIVES, THEN THE PRESIDENT; FOR AN ALASKA CONGESTION AREA, THE REGULATORY COMMISSION OF ALASKA

On November 19th the Senate passed H.R. 2347 as amended, 62 to 33, with Senators Murkowski and Sullivan voting yea. New Federal Power Act section 224(d), titled Alaska, lets the Secretary of Energy name an Alaska congestion area only subject to the approval of the Regulatory Commission of Alaska. New section 229 bars charging other customers for a data center's incremental cost, with no megawatt threshold. NPR reported on November 20th that the bill heads to the House.

There is no comment room on a bill. The route is the congressional delegation. If it becomes law, an Alaska congestion area needs the Regulatory Commission of Alaska's approval.
SEP 30S. 5653 introduced by Sen. Capito with Senators Lee, Whitehouse and Heinrich
NOV 19Senate passes H.R. 2347 as amended, 62 to 33, Murkowski and Sullivan yea
2026-11-26 · The Senate roll call list, read today, shows no action after passage on November 19th. The bill now needs the House to act on the Senate amendment. Checked and unchanged.

Decided

31
CLOSED STATE LAND LEASE next NOV 30

STAK Energy's North Slope AI campus lease

DECIDES · ALASKA DNR, DIVISION OF OIL AND GAS

DNR decided on November 10th to lease 715.4 acres about 26 miles south of Deadhorse to STAK Energy for 50 years, for a 1 to 3 gigawatt gas-fired data center. Rent is the larger of an appraised base or a surcharge on power delivered to compute, with no surcharge on the first 100 megawatts, then $0.20 to $0.40 per megawatt-hour, falling at the largest scales.

Decided November 10th. Timely commenters may request reconsideration within 20 days, and a court challenge is possible.
MAY 12Preliminary decision noticed (ADL 422741)
JUN 15Original comment deadline
JUN 17Comment period extended for volume and public interest
JUL 17Public comment closes, 4:30 p.m. AKDT
NOV 10DNR approves the 50-year lease
NOV 30Reconsideration requests due
2026-11-11 · Decided. DNR's Final Finding and Decision for ADL 422741, dated November 10th, approves a 50-year lease on 715.4 acres. Rent is the larger of an appraised base or a tiered surcharge on electricity delivered to compute, replacing the share of gross receipts first contemplated. DNR received 1,205 comments. The Alaska Beacon reports a 20-day reconsideration window.
32
INDIRECT LEGISLATION Closed

The AKLNG gas line tax bill

DECIDES · ALASKA LEGISLATURE, THIRD SPECIAL SESSION

A conference committee compromise unveiled July 2nd would swap the state property tax on the Glenfarne-led Alaska LNG project for a volumetric tax after five years of operation or 500 MMcf per day, and extend the completion deadline to the end of 2034. The House deadlocked 19 to 19 on July 16th over an expanded S corporation income tax, the governor rejected that provision, and a third special session convened July 27th with no bill from the governor and almost no legislators in the room.

Legislators decide; constituents reach them directly. The gas line would feed the grid most Alaska compute would ride on.
JUL 2Draft compromise unveiled
JUL 16Tentative House and Senate floor votes
JUL 19Special session ends
JUL 27Third special session convenes, 10:00 a.m.
AUG 10Senate could convene in full if the House passes a bill
AUG 12House Bipartisan Majority Caucus says HB 4001 lacks the votes to pass
AUG 13Governor says there is little reason to keep the third special session going
AUG 19Glenfarne says it is evaluating alternative paths after the tax effort fails
AUG 20Joint Senate and House Resources Committee meeting in Anchorage on Cook Inlet energy
AUG 25Third special session scheduled to end
2026-10-27 · Checked for news of the tax bill today. Nothing has moved since the third special session ended on August 25th; the next vehicle remains the Legislature seated in January under the governor elected November 3rd.
33
INDIRECT STATE LAND LEASE next NOV 30

AIDEA's free state land near Houston, cut to about 6,800 acres

DECIDES · ALASKA DNR, COMMISSIONER JOHN CROWTHER, ON AIDEA'S APPLICATION

On November 10th Natural Resources Commissioner John Crowther signed the Final Finding and Decision on ADL 234762. It conveys about 6,800 acres of state land about two miles north of Houston to the Alaska Industrial Development and Export Authority at no cost, down from 19,500 acres in the July 10th preliminary decision, for a multi-use industrial and energy development district. The final decision keeps a reversionary interest that the preliminary decision had waived, and voids the approval if AIDEA does not survey the land and complete the pre-patent requirements within 10 years. DNR received 2,306 public comments and eight from agencies. It says the conveyance does not approve any specific development, and that roads, power and other infrastructure would need their own approvals.

The decision is made. People who sent timely written comment may ask the commissioner to reconsider within 20 calendar days of the November 10th decision, which runs to November 30th, with a $200 fee, by mail, fax or dnr.appeals@alaska.gov. If the commissioner does not act within 30 days of the decision the request is considered denied, and a court challenge must start with that request. Anyone else can no longer change the decision at DNR. The lawsuit filed October 22nd in Superior Court at Juneau is still pending, and the next governor is sworn in December 7th.
JUL 13Preliminary decision reported
AUG 13Houston City Council rejects a data-center ban 4 to 2 and passes two resolutions objecting to the transfer process
AUG 19Original public comment period ends
AUG 26AIDEA board meeting, 9:00 a.m., Anchorage
AUG 27Public meeting on the conveyance, 6:00 p.m., on Zoom
SEP 1AIDEA asked to attend a Houston City Council meeting in September, no date set
SEP 2Second public meeting on the conveyance, 11:30 a.m., on Zoom
SEP 9Five Senate Resources Committee members write to DNR questioning the conveyance's legality
SEP 14Extended public comment period ends
SEP 15Matanuska-Susitna Borough Assembly votes unanimously to oppose the transfer
OCT 8Houston City Council hears a two-year moratorium on new data center construction
OCT 22Eric Forrer and David Eastman sue the State, DNR and the governor in Superior Court at Juneau, case 1JU-26-01019
OCT 26Crowther testifies to Senate Resources under subpoena and says approval before the inauguration is certainly possible
NOV 10Commissioner Crowther signs the Final Finding and Decision, about 6,800 acres
NOV 30Requests for reconsideration from timely commenters due, 20 calendar days after the decision
DEC 7The next governor is sworn in
DEC 10A reconsideration request not acted on within 30 days of the decision is considered denied
2026-11-17 · The Matanuska-Susitna Borough asked DNR on Friday, November 13th to reconsider the conveyance, in a letter signed by Mayor Edna DeVries and Manager Mike Brown, Alaska Public Media reported today. The borough says Point MacKenzie and parts of West Susitna are more appropriate locations and notes $180 million already spent on the Point MacKenzie rail bed. Reconsideration requests from commenters are due November 30th, and the decision stands unless the commissioner acts.
34
INDIRECT LEGISLATION Decided

Anchorage data-center zoning ordinance AO 2026-27

DECIDES · ANCHORAGE ASSEMBLY

On March 27th, 2026 the Anchorage Assembly adopted ordinance AO 2026-27 in a 10 to 2 vote, defining data centers in the municipal zoning code for the first time. It confines them to commercial and industrial zones, requires landscaping buffers and enclosed power equipment, and requires written statements from electric and water utilities that the grid has sufficient system capacity before a project proceeds. Members Scott Myers and Keith McCormick voted against it.

The elected Anchorage Assembly adopted the ordinance in a public 10 to 2 vote. Residents reach it through Assembly elections and public testimony.
MAR 27Assembly adopts AO 2026-27 (10 to 2)
2026-11-20 · Re-read ADN's account of the March vote. AO 2026-27 stands as adopted, 10 to 2. Unchanged.
35
CLOSED LEGISLATION Closed

HB 259, state utility standards for large data centers

DECIDES · ALASKA LEGISLATURE (HOUSE ENERGY COMMITTEE)

HB 259, introduced by Rep. Donna Mears in January 2026, would have set utility rate-setting guidelines and community benefit agreement standards for large energy use facilities such as data centers, and given the Regulatory Commission of Alaska new duties over them. The House Energy Committee heard it twice, on January 29th and February 3rd, 2026, taking testimony from Greensparc, GCI, the Alaska Municipal League and former Rep. Paul Seaton. It never advanced out of that committee, and it carried a second referral to House Community and Regional Affairs it never reached. The bill died with the 34th Legislature at sine die on May 20th, 2026. Alaska still has no statewide cost-allocation rule governing how a large data-center load is billed against other ratepayers, which leaves that question with the Regulatory Commission of Alaska and with individual utility boards.

The bill died when the Legislature adjourned. No public path remains to this vehicle. A constituent who wants these standards has to ask a legislator to introduce them again in the 35th Legislature, which convenes in January 2027.
JAN 20Prefile released, read the first time, referred to House Energy then Community and Regional Affairs
JAN 29First House Energy Committee hearing
FEB 3Second House Energy Committee hearing, last recorded action on the bill
MAY 2034th Legislature adjourns sine die, the bill dies in committee
2026-10-30 · The morning sweep of the Legislature's BASIS record still reports HB 259 in House Energy with a status date of January 20th. The bill died in committee at sine die on May 20th. Checked and unchanged.
36
CLOSED PROCUREMENT Decided

The Army's Janus microreactor program at Fort Wainwright

DECIDES · DEPARTMENT OF THE ARMY, RUNNING ITS SOLICITATION THROUGH THE DEFENSE INNOVATION UNIT

Fort Wainwright was one of nine Army posts short listed for a microreactor under the Janus program. On August 26th, 2026 the Army named the first five installations and their vendors, and Fort Wainwright was not among them.

Industry submissions were taken through the Defense Innovation Unit and are evaluated privately. No public comment period exists at this stage, and no vendor has been named for Fort Wainwright.
NOV 18 2025Army solicitation released through the Defense Innovation Unit
DEC 15 2025Industry submissions due
AUG 26Army names its first five Janus installations and vendors; Fort Wainwright is not selected
2026-10-31 · Re-read the DefenseScoop report today. The five Janus installations named on August 26th are Fort Bragg, Fort Campbell, Fort Hood, Fort Benning and Fort Drum, and Fort Wainwright is among the short-listed sites not chosen. Checked and unchanged.
37
INDIRECT UTILITY DECISION Closed

Copper Valley Electric's shelved nuclear reactor study

DECIDES · COPPER VALLEY ELECTRIC ASSOCIATION BOARD

Copper Valley Electric studied putting a 10 megawatt micro modular reactor into its isolated Glennallen and Valdez system, which is connected to no other utility and burns liquid fossil fuel for roughly a third of its power. The cooperative finished a pre feasibility study, published it, and then tabled the project indefinitely.

Copper Valley Electric is a member owned cooperative, so its board answers to ratepayers who elect it. The project is tabled, so there is nothing before the board to comment on now.
FEB 2 2022Study announced with Ultra Safe Nuclear Corporation
AUG 9 2023Board tables the project indefinitely
2026-11-07 · Re-read the cooperative's project page today. Its newest item is still the August 9th, 2023 release headed that the micro modular reactor project was tabled indefinitely, and nothing dated 2024 or later has been added. Checked and unchanged.
38
CLOSED DECISION Decided

The University of Alaska's 829 acres at Port MacKenzie, leased to the coal plant's campus

DECIDES · UNIVERSITY OF ALASKA LAND MANAGEMENT SIGNED THE LEASE; ANY LEASE OF THE BOROUGH'S OWN PORT LAND WOULD NEED THE MAT-SU BOROUGH ASSEMBLY

Terra Energy signed a 20 year lease with the University of Alaska in late May for 829 acres near Port MacKenzie, four parcels in Township 14 North, Range 4 West, Seward Meridian, for what the lease calls the Terra Energy Center Campus, a large-scale industrial park. The project is part of affiliate Flatlands Energy's plan for a coal plant near Skwentna, which the Department of Energy selected for $89 million in engineering funding and whose described loads include data centers. Rent is $20,000 in the first year, $60,000 a year in the second and third, and $586,000 a year once operations begin, targeted for 2030, with a 2 percent annual adjustment. Borough officials expect Terra to pursue about 1,000 acres of borough port land as well.

The university's notice of intent to lease took written comments from January 30th to March 2nd and named no tenant and no use. University land is exempt from the state's best interest finding, according to the Mat-Su Sentinel. The next public room is the Mat-Su Borough Assembly, if Terra asks to lease borough land at the port.
JAN 30University of Alaska posts its notice of intent to lease the four parcels
MAR 2Written comments on the notice close at 5 p.m.
MAR 17Mat-Su Assembly overrides the mayor's veto of RS 26-019, a joint marketing effort with Terra aimed at large power users including data centers
2026-11-08 · A news search today found nothing newer than the Alaska Journal of Commerce's October 26th republication of the October 6th report on the lease. Checked and unchanged.
39
CLOSED LEGISLATION Decided

Anchorage's surveillance rules for its police crime center

DECIDES · ANCHORAGE ASSEMBLY

Three Anchorage Assembly members, Keith McCormick, Sydney Scout and Vice Chair Daniel Volland, introduced an ordinance on August 18th, reported as AO-2026-108, that would write surveillance rules into Anchorage code, among them a case number for every search of surveillance data, deletion of individuals' data after two weeks unless it is evidence in an active investigation, a warrant before footage goes to out of state or federal agencies, limits on automatic license plate readers, and, in co-sponsor Scout's own words, Assembly approval before adding new surveillance capabilities including AI powered tracking or identification technology. It moves alongside a roughly $600,000 contract with ThunderCat Technology for equipment at the Real Time Crime Center, the system the Assembly funded with $11.8 million last year and which is designed to stream up to 750 camera feeds. The center opened in September 2025 with one employee and about 15 cameras.

The Assembly passed the ordinance on November 4th, so the vote is over. The new temporary oversight committee will meet publicly at least once a month for a year, which is the next public room where these rules get reviewed, and an Assembly member is the route to any change.
AUG 4McCormick asks the Assembly to postpone approval of the equipment contract, Scout agrees
AUG 18Ordinance introduced by McCormick, Scout and Volland
AUG 21Assembly work session on the Real Time Crime Center, 10:40 a.m.
SEP 1Public hearing at the Assembly meeting, the point at which the public can speak to it
SEP 3Assembly approves the crime center equipment appropriation 8 to 4
SEP 15Public testimony taken at the regular Assembly meeting, then the ordinance held
OCT 14Second Assembly work session on the ordinance and its alternative versions
OCT 20The Assembly takes the surveillance ordinance up again at its regular meeting
NOV 4Assembly passes AO 2026-108(S) as amended, 11 to 1
NOV 4Assembly creates a temporary APD oversight committee, 10 to 1
2026-11-05 · The Assembly passed the administration-backed substitute, AO 2026-108(S) as amended, 11 to 1 late on Wednesday night, November 4th, according to Alaska's News Source, which did not name the member voting no. An amendment by Vice Chair Daniel Volland and Sydney Scout to write a 14-day deletion deadline for plate reader captures and crime center video into municipal code failed, and an amendment requiring judicial warrants for retrospective plate reader searches failed 5 to 7. An amendment by Erin Baldwin Day, passed unanimously, requires 30 days of advance notice to the Assembly before APD makes a material policy change, and a change to data storage limits counts as one. APD's own policy already deletes plate data after 14 days. The same night the Assembly voted 10 to 1 to create a temporary committee, led by Kameron Perez-Verdia, to oversee APD policies, meeting at least monthly for one year (Anchorage Daily News). The as-amended text was not readable on the municipality's site today, which returned not found for every AO 2026-108 document.
40
CLOSED REGULATORY DOCKET next SEP 13 2027

The Navy's permit for an under-ice robot navigation grid

DECIDES · NOAA NATIONAL MARINE FISHERIES SERVICE, OFFICE OF PROTECTED RESOURCES

NMFS has authorized the Office of Naval Research to harass marine mammals incidental to Year 9 of its Arctic Research Activities in the Beaufort and Chukchi seas, and what the authorization covers is an acoustic navigation grid. Up to six moored sources at 900 to 950 Hz and two drifting ice gateway buoys will transmit a 30 second pulse every four hours for one year, so that gliders operating under sea ice can fix a position by trilateration from those sources rather than by dead reckoning. The study area is about 639,237 square kilometres across the US Exclusive Economic Zone, the high seas north of Alaska and part of the Canadian Exclusive Economic Zone, coming within 204 kilometres of the Alaska coast at its nearest point. A research cruise of 22 days is planned to begin September 22nd, 2026 aboard R/V Sikuliaq, US Coast Guard Cutter HEALY or another vessel, while the sound sources stay in the water for twelve months. The authorization covers Level B harassment only and states that take by Level A harassment is neither anticipated nor authorized.

The record on this one is shut. NMFS took comment for 30 days after publishing the proposed authorization on July 22nd, 2026 and received three comment letters, all from private citizens, then issued the authorization on September 10th, 2026. There is no open filing path now. The next door is the Year 10 renewal, which the Year 9 proposal already invited comment on inside its own action line, and no renewal notice has published. Anyone who wants standing in Year 10 should watch the Federal Register for a proposed authorization under docket RTID 0648-XF889 or its successor.
JUL 22Proposed authorization published at 91 FR 46055, opening a 30 day comment period
SEP 4Authorization signed by the Director of the NMFS Office of Protected Resources
SEP 10Authorization issued and published at 91 FR 57547
SEP 14Authorization takes effect
SEP 22First research cruise planned to begin, 22 days in September and October
SEP 13 2027Authorization expires, one year being the statutory maximum
2026-11-22 · Searched the Federal Register today for Office of Naval Research Arctic documents published since October 22nd and found none, so the authorization published September 10th stands with no correction or withdrawal. Checked and unchanged.
41
CLOSED LEGISLATION Decided

Mat-Su bans automated license plate readers

DECIDES · MATANUSKA-SUSITNA BOROUGH ASSEMBLY

Ordinance Serial No. 26-106 adopts a new borough code chapter, MSB 23.30, whose title states that it prohibits the acquisition, installation and operation of automated license plate reader systems and associated mass surveillance technology. Assemblymember Bernier moved to introduce it on September 1st and to set the public hearing. A motion to adopt carried on September 15th. The borough's legislative record contradicts itself on who moved adoption, its action text naming one member and its structured mover field another, so this record does not name that mover. It is a prohibition rather than a set of conditions, which makes it the opposite instrument to the surveillance rules the neighbouring Anchorage Assembly is weighing. The borough's legislative record carries no vote tally for either motion, only that each one passed.

The Assembly adopted the ordinance on September 15th, so there is no comment room left on this measure. The borough code it creates, MSB 23.30, is the public record of what was decided, and an Assembly member is the route to any change to it.
SEP 1Introduced by Assemblymember Bernier, who also moved to set the public hearing
SEP 15Public hearing at the Assembly meeting, 6 p.m., Assembly Chambers, Palmer
SEP 15Assembly adopts Ordinance Serial No. 26-106
2026-10-25 · Checked the borough's legislative record again today. Ordinance Serial No. 26-106 still shows as passed on September 15th, with no later action. Checked and unchanged.
42
INDIRECT LEGISLATION Decided

Kenai Peninsula Borough writes a weather modification code

DECIDES · KENAI PENINSULA BOROUGH ASSEMBLY

Ordinance 2026-35, sponsored by the mayor, would amend borough code to enact a new section, KPB 17.10.165, related to weather modification and geoengineering activities on borough lands. It was introduced on September 3rd, carried a September 15th agenda date in the Policies and Procedures Committee, and is set for public hearing on October 20th. A companion measure, Resolution 2026-046, is on the same agenda. The borough took up the subject after a California company flew drone based cloud seeding over the Kenai Peninsula in August. The ordinance would require ten items in a borough lease or land use permit application, prohibit the activity on borough lands open for casual use, and carry a $1,000 per day fine and a five year application ban for a missing closeout summary. Its reach is borough land; the August flight that prompted it was over state land. The borough's record now carries an October 6th agenda date in the Policies and Procedures Committee.

The Assembly enacted the ordinance as amended on October 20th, after its public hearing, and the new code section is in effect. It reaches borough land only.
SEP 3Ordinance 2026-35 introduced by the mayor
SEP 15On the Policies and Procedures Committee agenda
SEP 15Companion Resolution 2026-046 adopted, 7 yes, 0 no, 2 absent
OCT 6Policies and Procedures Committee agenda date recorded by the borough
OCT 20Public hearing on Ordinance 2026-35, the point at which the public can speak to it
OCT 20Assembly enacts Ordinance 2026-35 as amended
2026-11-22 · The borough's legislative record for Ordinance 2026-35, read today, still shows it enacted as amended on October 20th with no later action. Checked and unchanged.
43
INDIRECT LEGISLATION Closed

SB 250, who pays for a data center's power

DECIDES · ALASKA LEGISLATURE (HOUSE COMMUNITY AND REGIONAL AFFAIRS COMMITTEE HELD IT)

SB 250, introduced by Sen. Loki Tobin on February 18th, would have barred utilities from putting a data center's costs into anyone's rates unless those costs were recovered solely from the data center, and would have required the Regulatory Commission of Alaska to approve each data center contract. The Senate-passed version applied to data centers drawing 15 megawatts of peak demand from an electric utility. The Senate passed it 14 to 5 on May 16th, and the House Community and Regional Affairs Committee heard and held it on May 18th, its last recorded action.

The bill stalled in a House committee before the session ended. Any revival starts over in the next Legislature, where it goes to the legislators you elect on November 3rd.
FEB 18Introduced by Sen. Loki Tobin
MAY 16Senate passes CSSB 250(CRA) on reconsideration, 14 to 5 with one excused
MAY 18House Community and Regional Affairs hears and holds the bill, its last recorded action
2026-10-30 · The morning sweep of the Legislature's BASIS record still reports SB 250 in House Community and Regional Affairs with a status date of May 17th and no later action. Checked and unchanged.
44
CLOSED DECISION Decided

AIDEA's $25 million stake in microreactor maker NuCube

DECIDES · ALASKA INDUSTRIAL DEVELOPMENT AND EXPORT AUTHORITY

AIDEA agreed to buy $25 million of NuCube Energy's Class A shares at $9.25 each, which NuCube's filing calls about a 14.5 percent discount, with half a warrant per share at $11.50. AIDEA's release names data centers among the industries cheaper power could serve and names no Alaska site, utility, customer or date.

AIDEA announced the investment as made on October 21st. The company's merger filing describes AIDEA as its anchor investor. No public comment step was announced.
OCT 19NuCube files its announcement naming AIDEA as anchor investor
OCT 21AIDEA announces the $25 million equity investment
2026-10-28 · Read AIDEA's release and NuCube's SEC filing. The $25 million counts toward the $75 million minimum cash condition for NuCube's merger with Launch Two Acquisition Corp. AIDEA says project costs and energy savings will be determined as projects are developed.
45
INDIRECT REGULATORY DOCKET Decided

FCC lets GCI buy Quintillion's Arctic subsea fiber

DECIDES · FEDERAL COMMUNICATIONS COMMISSION, OFFICE OF INTERNATIONAL AFFAIRS

On October 20th the FCC approved, with conditions, the transfer of control of Quintillion's submarine cable landing license to GCI and denied Alaska Communications' petition to deny. The 1,176-mile Quintillion System connects Prudhoe Bay, Utqiagvik, Wainwright, Point Hope, Kotzebue and Nome, and its Nome to Homer Express extension adds landings at Emmonak, Hooper Bay and Naknek. Alaska Communications argued that GCI and Quintillion are the only middle mile providers for substantial portions of Western and Northern Alaska. The FCC found the concerns largely mitigated, citing the growing presence of low Earth orbit satellite providers, particularly Starlink, while acknowledging disagreement in the record over whether Starlink sells wholesale middle mile service in Alaska today. As conditions, GCI must honor Quintillion's existing contracts and pricing for the life of the system, may adjust prices for inflation only when Anchorage inflation tops 5 percent and no sooner than three years after closing, and must file larger contracts with the FCC for five to seven years. The deal carries a $310 million enterprise value. The order does not mention artificial intelligence or data centers.

The order is decided. Petitions for reconsideration or applications for review may be filed within thirty days of its October 20th release, under the FCC's own rules. GCI must give the FCC its larger wholesale and enterprise contracts on the Quintillion network under seal, so the prices stay out of public view.
OCT 20FCC approves the transfer with conditions and denies Alaska Communications' petition
NOV 9GCI completes the acquisition
NOV 19Thirty days from release, the window for petitions for reconsideration
2026-11-19 · The thirty day window for petitions for reconsideration of the FCC's October 20th order closes today, counted from the order's release. Checked and unchanged.

Deadline alerts, in your inbox

One email when a public comment window opens or a decision is about to land. Nothing else, ever. Unsubscribe any time.

All sources verified against claims. The data behind this page is public at docket.json.

Alaska AI keeps this docket current with the same kind of autonomous system it builds for Alaska businesses.