NOVEMBER 1ST · 9 SLIDES

Not how big. What it plugs into. Petersburg's draft rules

On Petersburg's downtown waterfront, the Ocean Beauty cannery has been shut since 2016. Its buyer also owns its 2-megawatt transformer.

The deck

SWIPE, SCROLL OR CLICK A SLIDE TO GO FULLSCREEN · 9 SLIDES

01 / 09
01 / 09

The story

The utility projected selling all 2 MW to a data center would cut 2028's 5 percent rate increase to 0. The Greensparc data center deal didn't finalize. The owner is still pursuing a small one.

On October 5th the Assembly unanimously told staff to draft a nine-month moratorium on data centers that make their own power or skip closed-loop cooling. Its sponsor called the off-grid diesel case "probably far-fetched." Grid-tied projects could still apply.

Swipe for the draft drawn as a switch, the cannery nameplate, the May rate math and both votes.

Petersburg's supplier also powers Wrangell and Ketchikan. Should each town decide what a data center may plug into, or should the three decide together?

What we verified

56 CLAIMS, EACH RE-FETCHED FROM ITS SOURCE BEFORE THIS DECK SHIPPED

  1. Petersburg resident Becky Knight urged the Assembly in a May 4th statement to enact a moratorium on cell towers and data centers until their impacts were analyzed.

  2. AEA estimates the Cook Inlet PowerLink transmission project will cost 413 million dollars.

    PRIMARYAlaska Energy Authority2026-10-15
  3. AEA has secured 269 million dollars for Cook Inlet PowerLink.

    PRIMARYAlaska Energy Authority2026-10-15
  4. About 142 million dollars of Cook Inlet PowerLink's cost is still to be identified.

    PRIMARYAlaska Energy Authority2026-10-15
  5. Cook Inlet PowerLink would include a submarine cable of about 40 miles between the Beluga area and the Kenai Peninsula.

    PRIMARYAlaska Energy Authority2026-10-15
  6. Cook Inlet PowerLink's initial 100 megawatt system would accommodate future expansion to 200 megawatts.

    PRIMARYAlaska Energy Authority2026-10-15
  7. Cook Inlet PowerLink targets a 2031 in-service date, with federally funded completion required by August 2032.

    PRIMARYAlaska Energy Authority2026-10-15
  8. Responses to AEA's submarine cable prequalification and request for information are due December 15th, after a virtual conference on November 4th.

    PRIMARYAlaska Energy Authority2026-10-15
  9. AEA will receive about 32.8 million dollars through the Department of Energy's Grid Resilience State and Tribal Formula Grant Program.

    PRIMARYAlaska Energy Authority2026-10-21
  10. Alaska's grid resilience allocation is the third largest among states, behind California and Texas.

    PRIMARYAlaska Energy Authority2026-10-21
  11. The grid resilience allocation was 12.8 million dollars more than AEA anticipated.

    PRIMARYAlaska Energy Authority2026-10-21
  12. Securing all of the grid resilience funds requires a 1.8 million dollar state match.

    PRIMARYAlaska Energy Authority2026-10-21
  13. The Department of Energy announced the Beluga to Healy transmission project would combine up to 150 million dollars in Defense Production Act funding with 268 million dollars in non-federal funding.

    PRIMARYU.S. Department of Energy2026-10-05
  14. EPA proposed on October 29th to approve Alaska's application for primary enforcement authority over Class VI carbon sequestration injection wells.

    PRIMARYFederal Register (EPA)2026-10-29
  15. Approval would let the Alaska Oil and Gas Conservation Commission issue and enforce Class VI permits.

    PRIMARYFederal Register (EPA)2026-10-29
  16. Comments on EPA's Alaska Class VI proposal must be received by December 14th.

    PRIMARYFederal Register (EPA)2026-10-29
  17. Alaska applied to EPA for Class VI primacy on May 22nd.

    PRIMARYFederal Register (EPA)2026-10-29
  18. The Petersburg Borough Assembly took up two data center items at its regular meeting on October 5th.

    REPORTKFSK Petersburg2026-10-05
  19. The Assembly directed the Borough Manager and staff to draft an ordinance for a nine-month moratorium on certain data center projects.

    REPORTKFSK Petersburg2026-10-16
  20. Vice Mayor Jeigh Stanton Gregor proposed the moratorium.

    REPORTKFSK Petersburg2026-10-05
  21. The proposed moratorium would restrict data centers that use on-site power generation.

    REPORTKFSK Petersburg2026-10-16
  22. The proposed moratorium would also cover data center facilities that don't use a closed-loop cooling system.

    REPORTKFSK Petersburg2026-10-16
  23. Under the moratorium proposal, developers could still apply for a building permit if their project would be on Petersburg's grid.

    REPORTKFSK Petersburg2026-10-16
  24. The Assembly approved Stanton Gregor's moratorium direction unanimously.

    REPORTKFSK Petersburg2026-10-16
  25. Assembly Member Jeff Meucci brought the second data center proposal.

    REPORTKFSK Petersburg2026-10-16
  26. The Assembly directed the manager to draft changes to the borough's zoning code, Title 19, to regulate data centers.

    REPORTKFSK Petersburg2026-10-16
  27. The Assembly approved Meucci's zoning proposal unanimously.

    REPORTKFSK Petersburg2026-10-16
  28. Both measures must return to the Assembly for consideration and public hearings before either can take effect.

    REPORTKFSK Petersburg2026-10-16
  29. The moratorium as proposed would apply across the entire borough except the City of Kupreanof.

    REPORTKFSK Petersburg2026-10-16
  30. Petersburg Borough incorporated 3,829 square miles when it became a borough in 2013.

    REPORTKFSK Petersburg2026-10-16
  31. The September moratorium proposal had been limited to the borough's municipal service area, which ends roughly nine miles south of town.

    REPORTKFSK Petersburg2026-10-16
  32. In September the Petersburg Planning Commission asked the Assembly for a year-long moratorium on data center applications or permits.

    REPORTKFSK Petersburg2026-10-16
  33. The Assembly considered the Planning Commission's moratorium request on September 21st.

    REPORTKFSK Petersburg2026-09-28
  34. The Assembly's vote on the year-long moratorium request ended in a 3 to 3 tie, so it failed.

    REPORTKFSK Petersburg2026-09-28
  35. Stanton Gregor called the possibility of a data center running on diesel-generated power and bypassing the grid probably far-fetched but worth noting.

    REPORTKFSK Petersburg2026-10-16
  36. Assembly Member Bob Martin said of the data center ordinance that 'we got to get something on the books.'

    REPORTKFSK Petersburg2026-10-16
  37. Petersburg's municipal utility department is drafting an ordinance to regulate large power users such as data centers.

    REPORTKFSK Petersburg2026-09-28
  38. Greensparc is a Silicon Valley-based company that builds small-scale data center facilities in communities with unused, stranded power and renewable energy.

    REPORTKFSK Petersburg2026-05-01
  39. Developer Andrew Mazzella owns the defunct Ocean Beauty Seafoods property on Petersburg's downtown waterfront.

    REPORTKFSK Petersburg2026-05-01
  40. Mazzella bought the former Ocean Beauty properties in 2024.

    REPORTKFSK Petersburg2026-05-01
  41. Mazzella also owns the 2-megawatt transformer that powered the cannery.

    REPORTKFSK Petersburg2026-05-01
  42. The Ocean Beauty cannery ceased operations in 2016.

    REPORTKFSK Petersburg2026-05-01
  43. Mazzella is penalized thousands of dollars a month by the borough utility department for not using the transformer's power.

    REPORTKFSK Petersburg2026-05-01
  44. Petersburg runs on hydropower.

    REPORTKFSK Petersburg2026-05-01
  45. Petersburg has its own hydro plant south of town but buys most of its power from the Southeast Alaska Power Agency.

    REPORTKFSK Petersburg2026-05-01
  46. The Southeast Alaska Power Agency supplies power to Petersburg, Wrangell and Ketchikan.

    REPORTKFSK Petersburg2026-05-01
  47. Petersburg's utility projected a 5 percent rate increase for 2028.

    REPORTKFSK Petersburg2026-05-01
  48. The utility's chart showed the 2028 projected increase falling to 0 percent if a full 2 megawatts were sold to a data center.

    REPORTKFSK Petersburg2026-05-01
  49. Petersburg's utility department estimated the data center would generate 1 to 2 million dollars in revenue a year.

    REPORTKFSK Petersburg2026-05-01
  50. Petersburg utility rates were projected to rise about 4 percent a year for several years, and the data center would lower that to about 2 percent.

    REPORTKFSK Petersburg2026-05-01
  51. The Greensparc proposal would use the former cannery's existing power service, and the utility said it had enough surplus power to support it.

    REPORTKFSK Petersburg2026-05-01
  52. Greensparc describes its cooling as a closed-loop system that works like a car radiator.

    REPORTKFSK Petersburg2026-05-01
  53. Greensparc CEO Sam Enoka said 'We're not drawing any water, and we're not putting any emissions out.'

    REPORTKFSK Petersburg2026-05-01
  54. The developer's business deal with Greensparc did not finalize, KFSK reported in late September.

    REPORTKFSK Petersburg2026-09-28
  55. Mazzella Alaska confirmed it is still pursuing a small-scale data center aligned with its initially announced plan.

    REPORTKFSK Petersburg2026-09-28
  56. A data center was proposed in Wrangell as part of a larger port development.

    REPORTKFSK Petersburg2026-05-01

Beats

This article is on Alaska data centers · Alaska power and the grid · Alaska land and permitting for AI. Each beat page keeps every decision and every article on that subject in one place.