NOVEMBER 20TH · 10 SLIDES

Two Land Rights Decided. One Still Open.

"It's hard to look at that and not call this rushed," Sen. Cathy Giessel said of DNR's Alaska LNG lease decision.

The deck

SWIPE, SCROLL OR CLICK A SLIDE TO GO FULLSCREEN · 10 SLIDES

01 / 10
01 / 10

The story

UPDATE. DNR approved a 50-year North Slope data center lease and decided to convey about 6,800 acres near Houston to AIDEA. The third is Alaska LNG's 800-mile gas line. Its comments close at 5:00 p.m. November 25th.

DNR proposes converting the line's two conditional leases into full leases. Per DNR, that is not a permit to build. Seven conditions stay as later gates.

Hearings run virtually November 23rd and in Anchorage November 24th. A decision could come before the December 7th handoff.

The three files, the hearing in quotes, the seven conditions, Houston at true scale and every window on one calendar are all here.

If conversion is not a permit to build, what do investors gain from having it before December 7th?

What we verified

96 CLAIMS, EACH RE-FETCHED FROM ITS SOURCE BEFORE THIS DECK SHIPPED

  1. The DNR Division of Oil and Gas newsroom posted the public notice of its analysis, proposed decision and hearings on the AKLNG conditional right-of-way lease conversions on October 23rd.

  2. The DNR newsroom links the AKLNG ROW Conversions Decision document.

  3. The DNR newsroom lists how to join a November 23rd public hearing at 6 pm on the AK LNG right-of-way lease conversion.

  4. DNR published a Final Finding and Decision on the land conveyance to AIDEA near Houston on November 10th.

  5. The AIDEA Houston conveyance under ADL 234762 covers approximately 6,800 acres.

  6. Only commenters who submitted timely written comments are eligible to request reconsideration of the Houston decision.

  7. The U.S. Fish and Wildlife Service published a proposed incidental harassment authorization for the Southern Beaufort Sea stock of polar bears.

  8. The IHA application came from the Alaska Industrial Development and Export Authority.

  9. AIDEA's seismic survey would use 12 rubber-tracked vibroseis vehicles.

  10. The survey would deploy 37,500 wireless autonomous recording devices.

  11. FWS proposes take of no more than 10 polar bears by Level B harassment and 2 by Level A harassment.

  12. Take of 12 polar bears is 1.32 percent of the Southern Beaufort Sea stock estimate of 907 animals.

  13. FWS ran 10,000 iterations of its polar bear take model.

  14. Comments on the proposed IHA must be received by December 17th.

  15. DNR's Analysis and Proposed Decision on converting the Alaska LNG conditional right-of-way leases is dated October 23rd and signed by Commissioner John Crowther.

  16. The decision covers two leases, the Alaska LNG Point Thomson Transmission Line lease ADL 421296 and the Alaska LNG GTP-Mainline-LF lease ADL 421297.

  17. DNR received the conversion request on October 2nd from 8 Star Alaska, LLC acting on behalf of the Alaska Gasline Development Corporation.

  18. The request asks DNR to convert two conditional leases issued under AS 38.35.100(b) to right-of-way leases under AS 38.35.100(a).

  19. Public notice of the conversion application was posted on October 5th.

  20. The Commissioner issued a Final Decision in March 2021 granting conditional leases while finding AGDC had not yet demonstrated sufficient technical or financial capability.

  21. DNR says conversion does not grant AGDC permission to start construction.

  22. DNR says conversion does not eliminate the seven conditions in the leases as requirements at later steps of the project.

  23. The seven conditions are financial capability, technical capability, existing land uses, plans for timber, water and material use, a construction management schedule, an executed highway use agreement and an executed contaminated sites agreement.

  24. DNR cites 8 Star's non-recourse financing structure and planned capitalization of more than $50 billion as a financial basis for the project.

  25. The project's Letters of Intent with seven international energy companies cover more than 60 percent of planned LNG capacity and are non-binding.

  26. AGDC and 8 Star submitted a confidential project economics analysis conducted by the Department of Revenue.

  27. AGDC keeps a 25 percent ownership stake in the project through 8 Star.

  28. DNR says AGDC's current Design Basis document is not a full preliminary design package.

  29. DNR says AGDC's application does not yet fully resolve third-party issues at the Mainline Material Offloading Facility on the west side of Cook Inlet.

  30. The Mainline lease must address existing uses including shorefish lease areas in Nikiski and the Little Troublesome Creek Campground in Denali State Park.

  31. DNR says that absent conversion, investors, in-state gas producers, Railbelt utilities, foreign LNG markets and Alaskans lack certainty of the state's commitment.

  32. DNR says conversion will assist the project to move closer toward a Final Investment Decision.

  33. Written comments on the proposed decision must be received by 5:00 p.m. on November 25th.

  34. A virtual public hearing is set for November 23rd from 6:00 p.m. to 8:00 p.m.

  35. An in-person hearing is set for November 24th from 11:00 a.m. to 1:00 p.m. at Alaska Housing Finance Corporation headquarters, 4300 Boniface Parkway, Anchorage.

  36. DNR's proposed decision finds the conditions for conversion have been met and that amending the leases is in the best interest of the state.

  37. AGDC secured Gas Sale Precedent Agreements with ExxonMobil, Hilcorp Alaska and ConocoPhillips for Phase One gas supply for up to 30 years, per DNR.

  38. The Mat-Su Borough asked DNR in a November 13th letter to reconsider its decision on ADL 234762.

  39. The Mat-Su letter describes the decision as a conveyance of approximately 6,800 acres of state land north of Houston to AIDEA.

  40. The Mat-Su request rests on Resolution Serial No. 26-103, adopted unanimously by the Assembly on September 15th.

  41. The Mat-Su letter says Point MacKenzie and portions of West Susitna offer more appropriate locations for the uses AIDEA contemplates.

  42. The Mat-Su letter names industrial, logistics, transportation, manufacturing, energy and resource-processing activities as AIDEA's contemplated uses.

  43. The Mat-Su letter says its request should not be read as opposition to AIDEA's broader economic-development mission.

  44. The Mat-Su letter is signed by Mayor Edna DeVries and Borough Manager Michael Brown.

  45. DNR's notice for ADL 422741 concerns a land lease application by STAK Energy Corporation.

  46. The STAK lease site is a 715.4-acre parcel adjacent to the Dalton Highway about 26 miles south of Deadhorse.

  47. Legislators questioned the Alaska LNG lease decision in a joint meeting of the House and Senate Resources committees on Tuesday.

  48. The proposed Alaska LNG pipeline is 800 miles long.

  49. The Alaska LNG project is expected to cost upwards of $50 billion.

  50. AGDC, a state entity, controls 25 percent of the Alaska LNG project.

  51. Glenfarne, a private company, owns the rest of the Alaska LNG project.

  52. DNR will accept public comments on the proposed Alaska LNG lease approval through November 25th.

  53. A decision on the Alaska LNG leases could come before Gov.-elect Jonathan Kreiss-Tomkins succeeds Dunleavy on December 7th.

  54. Sen. Cathy Giessel said "It's hard to look at that and not call this rushed."

  55. Giessel said "What's happening here doesn't feel very responsible to me."

  56. Giessel asked "When is an in-depth analysis going to be done?"

  57. Giessel said AGDC is considered a state entity "and yet they're only a 25% owner."

  58. Sen. Bill Wielechowski asked "What's the rush? Why not wait until the next administration gets in office?"

  59. Wielechowski said "AGDC has never built a thing."

  60. Sen. Matt Claman called it "a very disorganized and confusing process here in the last days of the Dunleavy administration."

  61. DNR Commissioner John Crowther said the department is "doing our best to advance (the decision) as expeditiously as we can."

  62. Crowther acknowledged DNR deviated from its normal process under state law for the Alaska LNG leases.

  63. Normally such a lease approval would require a detailed financial analysis of the project's feasibility.

  64. Crowther said he hopes the right-of-way "will induce and encourage further progress."

  65. AGDC President Frank Richards said investors "expect land rights in place to support construction and operations" before committing financing.

  66. Gov.-elect Kreiss-Tomkins said "Decisions of this magnitude deserve careful consideration and transparency that protects Alaskans' interests."

  67. The ADN article notes DNR separately approved a new lease for a data center on the North Slope.

  68. DNR approved a 50-year land lease for the STAK Energy Campus data center on the North Slope on Tuesday.

  69. The STAK data center complex is expected to cover about 715 acres.

  70. DNR described the STAK project as including a 1 to 3 gigawatt generation system.

  71. The STAK power plant would be fired with gas produced locally on the North Slope.

  72. Initial site development for the STAK Energy Campus is estimated to cost $500 million.

  73. DNR received more than 1,200 public responses on the STAK lease, most in opposition.

  74. The STAK lease decision is subject to a 20-day reconsideration period and could be challenged in court.

  75. STAK construction is expected to require a peak workforce of up to 1,500 workers.

  76. The Mat-Su Borough sent DNR a letter asking the state to reconsider transferring about 6,800 acres near Houston to AIDEA.

  77. The borough said Point Mackenzie and portions of West Susitna offer more appropriate locations.

  78. The state first proposed a much larger transfer of almost 20,000 acres.

  79. DNR received more than 2,300 public comments on the no-cost transfer, almost all opposed.

  80. Anyone who commented during the proposal process can request reconsideration of the Houston transfer by November 30th.

  81. DNR has 30 days to address the reconsideration requests.

  82. According to an AIDEA proposal, the Houston land could be used for an industrial hub or data centers.

  83. The Alaska Railroad board gave final approval for the $311 million Port MacKenzie rail line.

  84. The Port MacKenzie rail line will run 32 miles north from Cook Inlet.

  85. Alaska Railroad CEO Bill O'Leary said "Our goal is to really break ground this summer, but that is dependent upon a number of things."

  86. A coal-fired computing data center has announced a construction project at Port MacKenzie.

  87. AIDEA has not yet voted to approve its $33 million match for the rail line, and its board adjourned its meeting until November 24th.

  88. Kreiss-Tomkins is set to take office on December 7th, ten days after results are certified on November 25th.

    REPORTAlaska Beacon2026-11-20
  89. Gov.-elect Kreiss-Tomkins asked AIDEA to freeze any plans for additional spending before he takes office.

    REPORTAlaska Beacon2026-11-20
  90. The Fairbanks North Star Borough Planning Commission approved Mayor Grier Hopkins' proposed moratorium on permits for large-scale data centers.

  91. The commission extended the proposed moratorium from 12 months to 18 months.

  92. The commission increased the administration's research timeline from six months to 10 months.

  93. The Borough Assembly vote on the moratorium will likely take place on January 14th.

  94. Hopkins said the scale of data centers seen elsewhere "is relatively terrifying if you love your community."

  95. Hopkins said the clock for the 18-month moratorium will start once it takes effect.

  96. Hopkins said a data center built purely for a government purpose would likely not be subject to the moratorium.

Beats

This article is on Alaska data centers · Alaska land and permitting for AI · Alaska AI policy and legislation. Each beat page keeps every decision and every article on that subject in one place.