Petersburg's Three Data Center Tests, and the Wider Freeze
On November 2nd, Petersburg's draft data center freeze had three tests. On November 16th, a 5 to 2 vote widened it to every data center.
The deck
SWIPE, SCROLL OR CLICK A SLIDE TO GO FULLSCREEN · 9 SLIDES









The story
Three drafted tests, five Assembly tallies and the clock to 2027.
The tests were exact. The utility had to confirm in writing that today's grid could fully supply the load. No generators for everyday power. Coolant had to stay 100 percent in the loop.
Jeff Meucci's amendment tied 3 to 3 on November 2nd and passed two weeks later. The Petersburg Pilot says it closes the opening left for Mazzella's 2-megawatt project.
As of mid-November, Petersburg had no data centers. The final vote is scheduled for November 30th. A full pause is defensible.
The tests are worth keeping. If the freeze ends on September 30th, 2027, should they become the rules, or should Petersburg start over?
What we verified
58 CLAIMS, EACH RE-FETCHED FROM ITS SOURCE BEFORE THIS DECK SHIPPED
Ordinance 2026-24 passed its first reading by a vote of 5-1.
Ordinance 2026-24 as introduced was titled as a temporary moratorium on borough permits for certain data center development.
The ordinance defines a data center to include facilities whose principal use is artificial intelligence computing.
Under the ordinance, current grid capacity is the capacity Petersburg Municipal Power & Light determines in writing is available to the site.
The ordinance requires a qualifying closed-loop cooling system to keep 100 percent of its coolant and refrigerant circuits contained.
As introduced, the ordinance barred permits for a data center whose load PMPL's current grid capacity couldn't fully supply or that would breach a SEAPA limitation.
As introduced, the ordinance barred permits for a data center relying on diesel, natural gas or other generators for its normal operating load.
As introduced, the ordinance barred permits for a data center if any part of its cooling system was not fully self-contained and closed-loop.
The ordinance permits backup generators during an actual grid outage or a curtailment directed by PMPL.
The ordinance requires cooling plans certified by an Alaska-licensed professional engineer.
The Borough Manager must return findings and recommendations on data centers to the Assembly on or before June 21st, 2027.
The moratorium expires automatically at 11:59 p.m. Alaska time on September 30th, 2027, unless the Assembly extends or repeals it.
The review covers authority to apply future data center rules throughout the borough, excluding the City of Kupreanof.
The ordinance does not revoke a valid permit issued before its adoption.
The ordinance and its moratorium take effect upon adoption.
The moratorium applies even to applications pending on the date of adoption.
Ordinance 2026-25 would authorize up to $3,315,000 in electric utility revenue bonds for the Scow Bay Standby Generation Project.
Voters ratified the Scow Bay generation borrowing at an election on October 6th.
Borough staff recommended a special Assembly meeting on November 30th for the second reading of the bond ordinance.
AIDEA's November 24th board meeting went into recess.
The AIDEA board meeting is set to resume on Friday, November 27th.
The resumed AIDEA session is scheduled for 10 a.m.
The Petersburg Borough Assembly voted 5-2 to broaden the proposed data center moratorium so it would apply to all data center development.
Assembly Member Jeff Meucci proposed the amendment that broadened the moratorium.
Mayor Bob Lynn and Vice Mayor Jeigh Stanton Gregor voted against the broadening amendment.
The amended Ordinance 2026-24 passed its second reading unanimously, 7-0.
The moratorium needs one more round of Assembly approval before it can take effect.
The Assembly is set to take up the moratorium again on November 30th at 6 p.m.
The November 30th meeting will include another public hearing on the amended moratorium.
The additional public hearing was recommended by the borough attorney, according to the Petersburg Pilot.
The Petersburg Pilot reported that the amendment closes the opening left for Mazzella's 2-megawatt data center.
As amended, the moratorium applies whether a project runs on or off the local grid and whatever cooling system it uses.
Meucci argued for a full moratorium on any additional data center building permits.
Utility Director Steve Harbour helped write the ordinance.
Harbour said nobody wants generators running around the clock and that this is the purpose of the ordinance.
Assembly Member James Valentine said the moratorium gives the borough time and that he would vote yes.
Assembly Member Bob Martin said diesel generation was the biggest open door.
Stanton Gregor called the amendment a solution in search of a problem.
Mayor Bob Lynn is board chair of the Southeast Alaska Power Agency, the wholesale hydropower supplier.
At the November 2nd first reading, Meucci's amendment to cover all data centers failed in a 3-3 tie.
Member Donna Marsh seconded Meucci's November 2nd amendment.
Assembly Member Scott Newman was excused from the November 2nd meeting, when the moratorium advanced 5-1.
There were no data centers in Petersburg as of KFSK's November 11th report.
Harbour told the Assembly a generator ban was needed because a generator-powered data center was not out of the realm of possibilities.
KFSK reported that the moratorium as written would apply where the borough has platting authority.
Developer Andrew Mazzella owns the 2-megawatt transformer that powered the former Ocean Beauty cannery.
Petersburg runs on hydropower.
Petersburg buys most of its power from the Southeast Alaska Power Agency, which also supplies Wrangell and Ketchikan.
Petersburg's power department estimated in May that the waterfront data center could generate 1 to 2 million dollars in revenue a year.
The power department said in May the data center would lower Petersburg's projected annual rate increases from about 4 percent to about 2 percent.
Mazzella Alaska's deal with Silicon Valley data center vendor Greensparc did not finalize.
As of late September, Mazzella Alaska said it was still pursuing a small-scale data center.
On September 21st, an earlier year-long data center moratorium proposal deadlocked 3-3 in the Petersburg Assembly.
On October 5th the Assembly directed staff to draft an ordinance for a nine-month moratorium on certain data center projects.
When Petersburg became a borough in 2013, it incorporated 3,829 square miles of land.
The Fairbanks North Star Borough Planning Commission extended the mayor's proposed 12-month data center moratorium to 18 months.
The commission also lengthened the administration's research timeline from six months to 10.
Mayor Hopkins said the Fairbanks North Star Borough Assembly vote will likely take place on January 14th.