The Alaska AI Docket

Every AI infrastructure decision in Alaska, tracked daily. Who decides, when it lands, and whether the public gets a say. Sources on every item.

25
DECISIONS TRACKED
03
OPEN TO THE PUBLIC
SEP 14
NEXT DATE
Docket agentPUBLISHED RECORD / VERIFIED SENTENCES
TRY
NEAR

Model in training

The search writes from the published record and is checked against it line by line. If an answer missed something or read oddly, that is worth knowing.

George M Sullivan Generation Plant 2, 309.3 MW, natural gasBeluga, 300.4 MW, natural gasSouthcentral Power Project, 169.7 MW, natural gasEklutna Generation Station, 165 MW, natural gasNorth Pole, 145 MW, petroleumBradley Lake, 126 MW, hydroelectricSoldotna, 90.5 MW, natural gasSnettisham, 78 MW, hydroelectricHealy, 77.8 MW, coalNikiski Combined Cycle, 75.9 MW, natural gasHank Nikkels Plant 1, 62.4 MW, natural gasBernice Lake, 62.4 MW, natural gasLemon Creek, 57.5 MW, petroleumEklutna Hydro Project, 44.4 MW, hydroelectricBattery Energy Storage System, 40 MW, batteriesInternational Battery Substation (IBSS), 40 MW, batteriesFairbanks, 36.1 MW, petroleumUniversity of Alaska Fairbanks, 35.7 MW, coalTerror Lake Microgrid, 33.6 MW, hydroelectricAuke Bay, 28.3 MW, petroleumChena Power Plant, 25.7 MW, coalJarvis Street, 25.1 MW, petroleumEielson AFB Central Heat & Power Plant, 24.6 MW, coalEva Creek Wind, 24.6 MW, windIndustrial Plant, 23.5 MW, petroleumDelta Power, 23.1 MW, petroleumTNSG North Plant, 23.1 MW, natural gasS W Bailey, 23 MW, petroleumSwan Lake, 22.6 MW, hydroelectricTyee Lake Hydroelectric Facility, 22.6 MW, hydroelectricUtility Plants Section, 22.1 MW, coal 122 decisions at Anchorage31543 decisions at Fairbanks5817679101112132 decisions at Juneau141618
Transmission at 69 kV and up. The raw state layer is 93 percent local distribution from one utility, so it is cut at the transmission floor.Power plants of 20 MW and up. That is 31 of Alaska's 152 plants but 78 percent of its capacity. Circle area is nameplate megawatts.The Trans Alaska Pipeline System. Gas lines are left out, being 96 percent sub-kilometre distribution with nothing to sort them by.

Closing soon

The nearest deadlines and votes. A pulsing pin on the map means a public comment window is open right now.

The docket

Access reads OPEN when a formal public comment or testimony path exists today, INDIRECT when an elected or member-accountable body decides, CLOSED when the evaluation is private.

01
OPEN TO YOU STATE LAND LEASE by SEP 14

AIDEA's free state land for a Mat-Su data center park

DECIDES · ALASKA DNR, COMMISSIONER JOHN CROWTHER

A DNR preliminary decision would transfer about 19,950 acres, roughly 31 square miles, of state land about two miles north of Houston in the Mat-Su to the Alaska Industrial Development and Export Authority at no charge, a state subsidy meant to seed a multi-use industrial and energy district that AIDEA's own development plan describes as including scalable data centers, advanced manufacturing pads and a logistics hub on the Parks Highway and the Alaska Railroad, about 60 road miles north of Anchorage. Written public comment was to close August 19th and DNR extended it to September 14th.

The comment room is open and a second meeting is still ahead. DNR noticed public meetings on Zoom for August 27th, 2026 at 6:00 p.m. and September 2nd, 2026 at 11:30 a.m., both informational only, with no comment taken during the sessions. Written comment on ADL 234762 runs to 5 p.m. Monday, September 14th, 2026, and the division's notice ties appeal standing on the Final Finding and Decision to having filed timely written comment during the window. DNR says more than 2,000 written comments have arrived so far. Comments go to Dan Jenkins at the Division of Mining, Land and Water, 550 W. 7th Ave. Suite 1050, Anchorage. Houston's city council has asked AIDEA to a September meeting for which no date is set.
JUL 13Preliminary decision reported
AUG 13Houston City Council rejects a data-center ban 4 to 2 and passes two resolutions objecting to the transfer process
AUG 19Original public comment period ends
AUG 26AIDEA board meeting, 9:00 a.m., Anchorage
AUG 27Public meeting on the conveyance, 6:00 p.m., on Zoom
SEP 1AIDEA asked to attend a Houston City Council meeting in September, no date set
SEP 2Second public meeting on the conveyance, 11:30 a.m., on Zoom
SEP 14Extended public comment period ends, 5:00 p.m.
2026-09-12 · Re-verified against both state notices today. The original notice, Alaska DNR Online Public Notices id 224431, still prints its own first deadline of 5:00 p.m. Wednesday, August 19th, 2026, and the extension notice, id 224879, published August 19th, 2026, carries the operative one in its own capitals, extended comment period ends 5:00 p.m. Monday, September 14th, 2026. Two documents carry two dates and the later one governs. Written comment on ADL 234762 closes at 5:00 p.m. Monday, September 14th, 2026, two days from today, and both notices archive the day after. Only persons from whom the division receives timely written comment during the period are eligible to file an appeal of the Final Finding and Decision, so a reader who misses the window also loses standing.
02
INDIRECT DECISION decision SEP 14

The Kenai Peninsula school district's AI rulebook

DECIDES · KENAI PENINSULA BOROUGH SCHOOL DISTRICT BOARD OF EDUCATION

The Kenai Peninsula Borough School District is writing the rules for artificial intelligence in its 39 schools while the school year starts. Its Policy Review Committee took up AR 5131.9 Academic Honesty, a new administrative regulation the district says was brought forward in relation to the inclusion of AI, on August 3rd, 2026, with two competing drafts posted, one from Administration and one from board member Mica VanBuskirk. That same evening the full board took first readings on three more documents the district describes as revised for AI-related policy shifts, AR 5125 Student Records, BP 1114 Communication Using Electronic Media and BP 5131.9 Academic Honesty, plus AR 6161.4 Acceptable Use. Nothing in the package is adopted. The district told KBBI in July that it has spent 8,300 dollars to date on a three year MagicSchool subscription for students and staff, so the classroom AI tool was bought before the rulebook was finished. Upstream sits Alaska's Strategic Framework, Artificial Intelligence for K-12, issued by the Department of Education and Early Development, which means what Kenai adopts previews what other Alaska districts face.

An elected school board decides, and its regular meetings carry a public comment period. There is no formal comment window on these documents and no published date for a final vote, so an Alaskan reaches this one through a board member or from the podium at a meeting.
JUL 6AR 5131.9 first presented to the Policy Review Committee and postponed
AUG 3Committee takes up AR 5131.9 with two competing drafts, and the board takes first readings on four more documents that evening
AUG 19First student day of the 2026-27 year districtwide
SEP 14Board takes second reading and action on BP 5131.9 Academic Honesty, and first reading and action on AR 5131.9
2026-09-12 · Checked again, and one thing is new. All three documents sit on the consent agenda of the September 14th, 2026 regular business meeting rather than on the discussion calendar. BP 1114 Communication Using Electronic Media is item 10146, second reading and action. BP 5131.9 Academic Honesty is item 10147, second reading and action. AR 5131.9 Academic Honesty is item 10145, first reading and action. A consent agenda is adopted in a single motion, so unless a board member asks for an item to be pulled, the district's artificial intelligence rules are adopted without separate debate. Two days out.
03
INDIRECT LEGISLATION by SEP 15

Anchorage's surveillance rules for its police crime center

DECIDES · ANCHORAGE ASSEMBLY

Three Anchorage Assembly members, Keith McCormick, Sydney Scout and Vice Chair Daniel Volland, introduced an ordinance on August 18th, reported as AO-2026-108, that would write surveillance rules into Anchorage code, among them a case number for every search of surveillance data, deletion of individuals' data after two weeks unless it is evidence in an active investigation, a warrant before footage goes to out of state or federal agencies, limits on automatic license plate readers, and, in co-sponsor Scout's own words, Assembly approval before adding new surveillance capabilities including AI powered tracking or identification technology. It moves alongside a roughly $600,000 contract with ThunderCat Technology for equipment at the Real Time Crime Center, the system the Assembly funded with $11.8 million last year and which is designed to stream up to 750 camera feeds. The center opened in September 2025 with one employee and about 15 cameras.

There is a way in again. Must Read Alaska reported on September 7th, 2026 that the ordinance is AO-2026-108 and that Anchorage residents can testify on it at the Assembly's regular meeting on September 15th, 2026 or online. That number and that date come from one outlet, because the municipality's own agenda system refuses an automated request and the ordinance text is still not readable anywhere else. Anyone relying on this should confirm the item is on the agenda before showing up, and writing to an Assembly member remains the surer route.
AUG 4McCormick asks the Assembly to postpone approval of the equipment contract, Scout agrees
AUG 18Ordinance introduced by McCormick, Scout and Volland
AUG 21Assembly work session on the Real Time Crime Center, 10:40 a.m.
SEP 1Public hearing at the Assembly meeting, the point at which the public can speak to it
SEP 15Public testimony on AO-2026-108 at the regular Assembly meeting, in person or online
2026-09-12 · Checked and unchanged. The spending is approved and the rules are not. AO-2026-108 and the September 15th, 2026 testimony date still rest on one outlet, the Must Read Alaska opinion piece of September 7th, 2026, because the municipality's own agenda system refuses an automated request and the ordinance text can't be read anywhere else. Three days out. Anyone planning to testify should confirm the item is on the published agenda first, and writing to an Assembly member remains the surer route.
04
INDIRECT GRANT next SEP 26

A national AI institute for Native communities, and the Alaska lane that closed with it

DECIDES · ADMINISTRATION FOR NATIVE AMERICANS, HHS ADMINISTRATION FOR CHILDREN AND FAMILIES

The Administration for Native Americans published its final Fiscal Year 2026 program policies on July 28th, 2026, standing up three funding opportunities and leaving out SEDS-AK, the Alaska-specific economic development program that ran alongside SEDS for decades. Two days later it posted the AI3 Action Institute, a single national award of up to $3,500,000 to build an artificial intelligence resource center for Native communities, with Alaska Native villages under ANCSA and nonprofit village consortia named as eligible applicants.

Only eligible applicants reached this one, and applications closed on August 27th, 2026, so no public path remains. An Alaskan reached it through a tribe, an ANCSA village or a Native nonprofit that filed in time. Applications are evaluated privately and no awardee has been named.
JUL 28Final Fiscal Year 2026 issuance published at 91 FR 47241, standing up EAGLE, the AI3 Action Institute and NCNTTA
JUL 28EAGLE posted, $24,000,000 across about 31 awards, applications due August 27
JUL 30AI3 Action Institute posted, one award, ceiling $3,500,000
AUG 27Applications close on both EAGLE and the AI3 Action Institute
SEP 26The posted opportunity is archived
2026-09-09 · Checked. Grants.gov shows the Economic Advancement Grants for Local Empowerment opportunity, HHS-2026-ACF-ANA-NEG-0120, closed on August 27th, 2026 with no award announced and no intent to award posted, against an award ceiling of $1,000,000 and about 31 expected awards. That is the same closing date the AI3 Action Institute posting carries. Until an award is published nothing shows who applied to either, and both postings are archived on September 26th, 2026, seventeen days out.
05
OPEN TO YOU REGULATORY DOCKET by SEP 30

The FCC asks whether AI should help run the Universal Service Fund

DECIDES · FEDERAL COMMUNICATIONS COMMISSION

The FCC published a notice on August 31st, 2026 seeking comment on how the Universal Service Fund is administered, and nine of its sentences name artificial intelligence. It asks whether AI tools used to review applications, audits and appeal review processes would reduce delays while maintaining accurate results, and whether the fund's administrator should expand use of AI in document review for audits and program compliance. One paragraph poses eight consecutive questions about AI. The Commission is asking rather than proposing, and every AI sentence in the notice is phrased as a question. The same notice seeks comment on cutting the administrator's board from 20 members to 13. Alaska is not named anywhere in it. Alaska's stake is in a companion notice published the same day, WC Docket No. 17-310, which reports that only 34 of 340 approved Telecom Program requests in Alaska in funding year 2025 relied on the Commission's preferred Methods 1 or 2, so the great majority of Alaska's rural health connectivity requests are justified the longer way. That is the paperwork an automated reviewer would read.

Anyone may file. Comments are due on or before September 30th, 2026 and reply comments on or before October 30th, 2026, in WC Docket No. 26-173, through the Commission's electronic filing system under 47 CFR 1.415 and 1.419. The notice gives Alaska no separate deadline and no separate route, so an Alaska clinic, school district, library or carrier files on the same clock as everyone else.
AUG 6Adopted by the Commission
AUG 7Released
AUG 31Published in the Federal Register at 91 FR 55826
SEP 30Comments due, WC Docket No. 26-173
OCT 30Reply comments due
2026-09-12 · Re-read the Federal Register text at the source. Comment in WC Docket No. 26-173, FCC 26-52, printed at 91 FR 55826 to 55835, is due on or before September 30th, 2026, and reply comments are due on or before October 30th, 2026. The notice was adopted August 6th, 2026 and released August 7th. Eighteen days are left in the comment window and nothing in it has moved.
06
OPEN TO YOU REGULATORY DOCKET by NOV 2

DeepGreen's underwater data center in Cook Inlet

DECIDES · FEDERAL ENERGY REGULATORY COMMISSION

DeepGreen Cook Inlet SPV LLC, a Delaware company whose parent formed in January 2026, applied to FERC in February for a preliminary permit over an initial operational envelope of 1,650 acres of Cook Inlet seabed west of Nikiski, proposing a 100 megawatt data center of 66 hives of AI servers powered and cooled by approximately 330 to 350 tidal turbines in water 45 to 166 feet deep. A preliminary permit authorizes study rather than construction, for up to four years, and FERC's Northwest branch found the application incomplete in a June 18th letter.

The comment room is open. FERC accepted DeepGreen Cook Inlet SPV, LLC's preliminary permit application for filing and published notice in the Federal Register on September 4th, 2026, opening the record on Project No. P-15423-000. Comments, motions to intervene, competing applications and notices of intent to file competing applications are due by 5:00 p.m. Eastern Time on November 2nd, 2026, which is 1:00 p.m. Alaska time. Filing runs through FERC's eFiling system and the docket is readable through eLibrary. A preliminary permit grants study and site priority rather than authority to build, so what is open here is the record on whether the applicant gets up to four years of priority to study the site.
FEB 11Preliminary permit application filed with FERC
JUN 18FERC's Northwest branch finds the application incomplete
JUN 26Application supplemented
AUG 19First Alaska reporting on the filing
SEP 4FERC accepts the application for filing and publishes notice in the Federal Register
NOV 2Comments, motions to intervene and competing applications due, 5:00 p.m. Eastern
2026-09-10 · Re-verified against the Federal Register notice of September 4th, 2026. The record on Project No. P-15423-000, DeepGreen Cook Inlet SPV, LLC, stays open until 5:00 p.m. Eastern Time on November 2nd, 2026 for comments, motions to intervene, competing applications and notices of intent to file competing applications. The notice describes approximately 330 to 350 marine hydrokinetic turbines and an estimated 100 megawatts of annual generation. The Commission contact is Christopher Brosman at 202-502-8573.
07
INDIRECT LEGISLATION next JAN 19 2027

Fairbanks asks Juneau and Congress to pause data centers

DECIDES · ALASKA LEGISLATURE AND THE ALASKA CONGRESSIONAL DELEGATION

On August 27th, 2026 the Fairbanks North Star Borough Assembly adopted Resolution 2026-25, its list of 2027 state and federal legislative priorities, sponsored by the Assembly Committee of the Whole. The list carries 25 items, 21 state and 4 federal, and one item appears on both halves. It asks for a moratorium on the permitting, leasing or construction of new commercial data centers on state-owned or municipal lands in Alaska until standards exist for electrical demand, water consumption and shortages, environmental impacts, noise, air quality and land use pollution. Assemblymember Garrett Armstrong moved it onto the state list at an August 6th work session and an amendment replicated it onto the federal list. The request follows the Air Force offer of about 4,700 acres across twelve parcels at three Alaska installations, one of which, Eielson, is inside this borough. The adopted text reaches state and municipal land, not federal land, and KUAC reports Presiding Officer Scott Crass said by phone that federal land was intended too.

The borough has already voted, so the room that was open is closed. What the resolution does is hand the question to two bodies that have not acted on it. A reader who wants the moratorium considered asks a legislator to carry it when the Legislature convenes in January 2027, or asks the congressional delegation to take up the federal half. The resolution itself, its full text and the meeting record are public through the borough clerk.
AUG 6Armstrong moves the moratorium onto the state list at a Committee of the Whole work session
AUG 20Committee of the Whole takes up the priorities list
AUG 27Assembly adopts Resolution 2026-25
JAN 19 2027The 35th Alaska Legislature convenes, the earliest the state half can be taken up
2026-09-09 · Checked and unchanged. Resolution 2026-25 was adopted on August 27th, 2026 and the moratorium request is still the one item standing on both the state and the federal half of the borough's 25 priorities. Mayor Grier Hopkins told Alaska's News Source the borough heard the community loud and clear, and that residents want it worked out how data centers can best be regulated and where, if anywhere, they should go in the borough. The state half can't be taken up before the 35th Alaska Legislature convenes on January 19th, 2027.
08
CLOSED STATE LAND LEASE Pending decision

STAK Energy's North Slope AI campus lease

DECIDES · ALASKA DNR, DIVISION OF OIL AND GAS

A preliminary decision would give STAK Energy a 50-year lease on 715.4 acres of state land about 26 miles south of Deadhorse for a gas-fired AI and cloud campus its developer pegs at more than $10 billion, with 1 to 3 gigawatts of on-site generation. More than 500 public comments arrived before the first deadline; fewer than a dozen supported the project.

The written comment window closed 4:30 p.m. July 17th, 2026. DNR now weighs more than 500 comments before a final best-interest decision on the 50-year lease. No public comment path remains open.
MAY 12Preliminary decision noticed (ADL 422741)
JUN 15Original comment deadline
JUN 17Comment period extended for volume and public interest
JUL 17Public comment closes, 4:30 p.m. AKDT
2026-09-11 · Checked and unchanged against the preliminary decision notice, Alaska DNR Online Public Notices id 224224. The notice still describes a 50 year lease offer to STAK Energy Corporation on 715.4 acres about 26 miles south of Deadhorse, for a commercial natural gas powered energy facility including modular high performance computing units. Comment closed at 4:30 p.m. on July 17th, 2026. No final finding and decision has been issued and none is scheduled. The notice says a copy will be sent to every person who commented, with an explanation of the appeal process, which is the only forward path the record names.
09
CLOSED FEDERAL LEASE Pending decision

Air Force land leases for AI data centers at JBER, Eielson and Clear

DECIDES · DEPARTMENT OF THE AIR FORCE, ENHANCED USE LEASE PROGRAM

The Air Force offered about 4,700 acres across 12 parcels at Joint Base Elmendorf-Richardson, Eielson AFB and Clear Space Force Station for privately financed AI data centers. Residents near the five Eielson-area parcels raised noise, permafrost and grid concerns, including one parcel less than a mile from North Pole Middle School.

Proposals closed in the spring and are evaluated privately. No public comment period exists and no award timeline has been announced. The solicitation record is public and carries no awardee.
APR 10Program announced
JUN 29Developer proposals due, 5 p.m. Eastern
JUL 14Solicitation record archived with no award posted
JUL 22U.S. House passes FY2027 NDAA carrying a data center lease restriction
JUL 23Bill introduced in the U.S. House to ban AI data centers on federal land
AUG 10Proposals due on a separate Eielson mixed-use lease covering 3,967 acres
2026-09-10 · Checked and unchanged. The enhanced use lease offering still stands as posted, about 4,700 acres across 12 parcels at Joint Base Elmendorf-Richardson, Eielson Air Force Base and Clear Space Force Station, with leases running up to 50 years and proposals having been due May 29th, 2026. The Air Force set no public selection or award date when it posted the offering, and none has been announced since, so a decision here arrives without a calendar.
10
INDIRECT UTILITY DECISION Pending decision

GVEA's $80 million turbine decision

DECIDES · GOLDEN VALLEY ELECTRIC ASSOCIATION BOARD OF DIRECTORS

Golden Valley Electric Association is weighing a 60 megawatt naphtha fueled turbine estimated at $80 million, to be installed beside an existing LM6000 at the co-op's North Pole Expansion plant. Its board voted on August 25th, 2026 to keep the purchase alive and to keep studying the risks and the alternatives.

A member-owned co-op board decides, in executive session. GVEA members reach it through board elections and member comment periods at regular meetings.
JUL 13Board weighs the purchase in executive session
AUG 25Board votes 4 to 3 in Delta Junction to move ahead on a possible purchase and to keep studying alternatives
2026-09-11 · Checked and unchanged against KUAC's account of the August 25th, 2026 board meeting. The 4 to 3 vote stands, with Rick Solie, Brad Swope, Krista Zappone and John Sloan in favour and Dave Messier, Gary Newman and Phil Wight opposed. Chief executive Travis Million said the co-op would return to the board if the unit falls through or the price goes through the roof, which puts the actual purchase decision still ahead. Board chair Messier said the matter would be considered further at the following month's meeting. No date for that has been published, so there is still no scheduled decision on the $80 million purchase.
11
INDIRECT REGULATORY DOCKET Pending decision

Enstar's Cook Inlet gas storage plan (Kenai Loop Pool)

DECIDES · REGULATORY COMMISSION OF ALASKA (PRUDENCY); ALASKA DNR (STORAGE LEASE AND TECHNICAL DETERMINATION)

On July 10th, 2026 the Anchorage Daily News reported the RCA issued a 17-page order denying Enstar's request for an advance determination that its proposed Cook Inlet gas storage project was prudent, saying the utility lacked basic information. The $240 million project would have bought the depleted Kenai Loop Pool reservoir from AIX Energy to hold 25 billion cubic feet of gas, close to half Enstar's annual demand, adding up to $12 a month to the average bill. Enstar and Hilcorp have competing DNR lease applications for the same pool, and DNR has not confirmed it is technically capable of storing gas. Without approval, Enstar president John Sims said the company suspended the project. Enstar reopened the question on July 23rd, 2026 with a 31-page petition for reconsideration, arguing the order was erroneous and suffers from a lack of true understanding of the nature of the problem, and calling the Kenai Loop Pool the only viable commercial storage option in Cook Inlet. Alaska Public Media reports the commission has thirty days to respond and that inaction is an automatic denial.

The RCA is a governor-appointed, legislature-confirmed commission, and the public reaches its dockets through formal comment and intervention. The prudency question is open again on Enstar's petition for reconsideration. The underlying DNR storage-lease question is also still open.
JUL 10RCA denies Enstar advance determination of prudency (ADN report); Enstar suspends the project
JUL 10DNR determination on Kenai Loop Pool storage capability and competing Enstar/Hilcorp leases still pending
AUG 21RCA denies reconsideration 3 to 2, with a written order to follow
AUG 22RCA acts on Enstar's petition for reconsideration, or the petition is denied automatically
2026-09-11 · Checked and unchanged. Nothing new has been posted since the August rulings. The record still runs from the Regulatory Commission of Alaska's July order denying Enstar an advance determination of decisional prudence for the Kenai Loop Pool project, through Enstar's 31 page petition for reconsideration filed July 23rd, 2026, to the denial of that petition in August. Enstar's own description of the reservoir, in president John Sims's words, is that it is "almost perfect for what Enstar views as short term and long term needs". The estimated $240 million cost would be the largest single capital investment in the utility's history, and Southcentral goes into this heating season without the storage it would have added.
12
INDIRECT DECISION Watching

The AI ratepayer pledge, and which Alaska utilities have signed it

DECIDES · EACH ALASKA ELECTRIC UTILITY BOARD, INCLUDING THE RAILBELT COOPERATIVES

The White House Ratepayer Protection Pledge asks AI companies, utilities and data center developers to commit that new data center load pays for its own generation and delivery instead of shifting the cost onto households. USA TODAY and POWER both describe it as voluntary and non binding. Gov. Mike Dunleavy signed the governors addendum on July 23rd, 2026, one of 23 governors. The signatory list has grown from 281 when it was first read here on July 26th, 2026 to 317 on September 11th, 2026, and across that growth exactly one Alaska entity appears on it, Cordova Electric Cooperative, a 1,566 customer cooperative that is not connected by transmission line to any other community. No Railbelt utility has signed.

Alaska's electric cooperatives are governed by boards their own members elect, so a member can ask their board directly whether it intends to sign. A voluntary federal pledge has no public comment docket, which is why this room is indirect rather than open.
MAR 4Pledge first signed by seven AI companies at the White House
JUL 23Governors addendum signed, Dunleavy among 23 governors
JUL 26Signatory list read at 281, one Alaska entity on it
2026-09-11 · Re-read directly off the White House page today, enumerating the list rather than the summary counts. The pledge now carries 317 signatories, up from the 281 read here on July 26th, 2026. The governors addendum still stands at 23 signatures, Governor Mike Dunleavy among them. Cordova Electric Cooperative remains the only Alaska entity on the list, and no other Alaska utility appears, with Chugach Electric, Golden Valley Electric, Matanuska Electric and Homer Electric all absent. The pledge is still voluntary. Its own language is that companies voluntarily negotiate new, separate rate structures with their utilities and state governments, which is a commitment to bargain rather than a rule about who pays. The growing count is recorded here in the summary rather than as a dated event, because a reading is an observation and not something a reader can act on.
13
CLOSED PROCUREMENT Pending decision

Alaska's statewide speech-to-text contract

DECIDES · ALASKA DEPARTMENT OF ADMINISTRATION, OFFICE OF PROCUREMENT AND PROPERTY MANAGEMENT

Alaska is soliciting one statewide contract to convert speech, live or recorded, into written text for general, medical and legal records. The notice says every state governmental entity may use the resulting contract, naming the Legislative Branch, the Court System, the University of Alaska, boards and commissions, cities, boroughs, school districts and federally recognized tribes. The public notice does not use the terms artificial intelligence, machine learning or automated speech recognition.

A vendor solicitation, not a rulemaking, so no public comment period exists. Proposals closed August 28th and are evaluated privately. The notice and the named procurement officer are public, though the notice's own archive date has now passed. No award has been posted.
JUL 31Solicitation published on the state public notice system
AUG 28Vendor proposals due, 3:30 p.m. Alaska time
2026-09-09 · Checked and unchanged. RFP 2026-0200-0064, Statewide Transcription Services, closed to proposals at 3:30 p.m. Alaska daylight time on Friday, August 28th, 2026. That deadline was set by Amendment 1 on August 17th, which also answered questions from the pre-proposal conference and moved the date from August 24th. The notice archived on August 31st and carries no intent to award, no award and no cancellation. The contracting officer of record is Joshua Hartman at the state Office of Procurement and Property Management.
14
CLOSED PROCUREMENT Watching

DMV asks vendors about automated compliance for commercial licenses

DECIDES · ALASKA DEPARTMENT OF ADMINISTRATION, DIVISION OF MOTOR VEHICLES

The Division of Motor Vehicles asked vendors for products, services, technical approaches and industry best practices related to automated compliance and data integration systems supporting the commercial driver's license program. The public notice does not use the terms artificial intelligence or machine learning.

A request for information gathers vendor input before any solicitation. There is no public comment path and no decision is made at this stage.
JUL 30Request for information published
AUG 20Vendor responses due, 2 p.m.
2026-09-10 · Checked and unchanged. The state notice for request for information 02-101-27, Automatic Compliance and Data Integration CDL, still shows Amendment One as the current posting, with responses due at 2:00 p.m. on August 20th, 2026 and an archive date of August 21st, 2026. No award, cancellation or follow-on solicitation has been posted.
15
CLOSED REGULATORY DOCKET Pending decision

The Dixon Glacier diversion into Bradley Lake

DECIDES · FEDERAL ENERGY REGULATORY COMMISSION

The Alaska Energy Authority has asked FERC to amend the license for the Bradley Lake Hydroelectric Project, the largest in Alaska, so it can build a new dam diverting meltwater and surface runoff from the Dixon Glacier into Bradley Lake, raise the lake's normal maximum operating pool by about 16 feet, and install a 0.3 megawatt micro-hydro turbine in one of the dam's fishwater release valves. The application projects about 38 percent more average annual generation while installed capacity rises from 119.7 to 120.0 megawatts, because the gain comes from water rather than from turbines. AEA estimates construction at about $400 million and about three years of study and permitting followed by three years of construction. FERC accepting the application for filing is a procedural step and not an approval.

The comment window has closed. Anyone could file a comment, a motion to intervene or a protest in docket P-8221-124 until 5:00 p.m. Eastern on August 28th, 2026, which was 1:00 p.m. Alaska time, and that hour has passed. FERC now weighs the application and has published no decision date. The docket itself stays readable through FERC's eLibrary, so an Alaskan can follow what was filed without being able to add to it.
JUN 30Amendment application filed with FERC
JUL 23AEA board endorses a financing package for the expansion
AUG 3FERC notice published in the Federal Register
AUG 28Comments, motions to intervene and protests due, 5:00 p.m. Eastern
2026-09-09 · Checked and unchanged. The Alaska Energy Authority's own project page still carries the Final License Amendment Application filed with FERC on June 30th, 2026 as its most recent development, and puts estimated construction cost at approximately $400 million. Comments, motions to intervene and protests closed at 5 p.m. Eastern on August 28th, 2026, and no FERC action on the amendment has been published since. Nothing here has a scheduled next date, so a ruling would arrive unannounced.
16
CLOSED PROCUREMENT Pending decision

The Air Force nuclear microreactor at Eielson

DECIDES · DEPARTMENT OF THE AIR FORCE WITH DEFENSE LOGISTICS AGENCY ENERGY, AND THE NUCLEAR REGULATORY COMMISSION FOR THE LICENSE

The Air Force intends to award Oklo a 30 year fixed price power purchase agreement for a microreactor delivering up to 5 megawatts to Eielson Air Force Base outside Fairbanks. Oklo would build, own and operate it, and the contract is signed only after Oklo obtains a license from the Nuclear Regulatory Commission.

Contract negotiation is private and the Air Force runs no comment period. The reactor can't be built without a Nuclear Regulatory Commission license, and that review is the room where the public gets a formal say.
JUN 11 2025Air Force announces a notice of intent to award to Oklo
2026-09-10 · Checked and unchanged. The notice of intent to award Oklo a 30 year firm fixed price agreement for up to 5 megawatts at Eielson is still a notice rather than a signed contract. Environmental analysis, contract negotiation and a Nuclear Regulatory Commission license all remain ahead of it, and the Air Force has put the reactor in service before 2030 without naming a nearer date.
17
CLOSED DECISION Watching

The executive order that lets big data centers skip the usual federal review

DECIDES · THE PRESIDENT, CARRIED OUT BY THE COUNCIL ON ENVIRONMENTAL QUALITY AND THE INTERIOR, ENERGY AND DEFENSE DEPARTMENTS

Executive Order 14318, Accelerating Federal Permitting of Data Center Infrastructure, directs federal agencies to speed approvals for data centers adding more than 100 megawatts of load or costing at least 500 million dollars. It tells agencies to find and create categorical exclusions under the National Environmental Policy Act, and directs Interior and Energy to offer federal sites while Defense may competitively lease military land.

An executive order takes no public comment. Its effect is to remove review steps that would otherwise have carried one, so the room this closes is the environmental review a project would have had.
JUL 23 2025Order signed
JUL 28 2025Published in the Federal Register
2026-09-11 · Checked and unchanged against the order's full text, read through the Government Publishing Office rather than the Federal Register site, which refuses an automated request. Executive Order 14318 of July 23rd, 2025 names no state and the word Alaska does not appear in it. Its deadlines all ran from the signing date and have all passed, 10 days for agencies to identify categorical exclusions to the Council on Environmental Quality, 180 days for the Environmental Protection Agency to develop guidance on expediting environmental reviews, and 180 days for the Army to review the nationwide permits. What reaches Alaska is the general machinery, not a provision written for it.
18
CLOSED GRANT Pending decision

An 89 million dollar federal grant for a coal plant in the Susitna watershed

DECIDES · U.S. DEPARTMENT OF ENERGY MADE THE SELECTION; THE PLANT ITSELF NEEDS STATE AND FEDERAL PERMITS NOBODY HAS APPLIED FOR YET

The Department of Energy selected Terra Energy Center Corporation of Anchorage, an affiliate of Flatlands Energy, for an 89 million dollar grant to study a 1,250 megawatt coal fired power plant west of Skwentna, with a 60 mile pipeline carrying its carbon dioxide to Beluga for injection into a depleted gas reservoir. The money funds a viability assessment rather than construction, and Terra must match it.

The grant selection carried no public comment period. Comment rooms open later, when the mine, the plant, the pipeline and the injection well each need their own permits.
JUN 4Federal grant selection announced
2026-09-11 · Re-verified against the Department of Energy's own selection page. The Alaska Carbon Capture, Utilization, and Storage Coal Commissioning Project is still listed at $89,000,000 with Terra Energy Center Corporation of Anchorage as the selectee and the facility sited in the Matanuska-Susitna Borough. The page is a list of selections and says nothing about the award being finalized. What it does say about timing is that the project aims to complete FEL-3, or Class 3, engineering in 2027, so no construction decision is near.
19
CLOSED REGULATORY DOCKET Pending decision

Alaska's bid to run its own carbon storage permits

DECIDES · ALASKA OIL AND GAS CONSERVATION COMMISSION APPLIES; THE U.S. ENVIRONMENTAL PROTECTION AGENCY DECIDES

The Alaska Oil and Gas Conservation Commission is applying to the Environmental Protection Agency for primary enforcement authority over Class VI wells, the wells used to inject carbon dioxide for permanent underground storage. If the application succeeds the state, not the federal government, would permit and police every carbon storage well in Alaska.

The state comment window closed at the end of the May 14th, 2026 hearing. The federal review of the application carries its own comment period, which has not opened.
MAR 3Public meeting on adopting the state regulations
MAY 14State hearing, and the close of written and oral comment
2026-09-11 · Checked. The commission's own carbon storage page again answered an automated request with a 403, so this was verified against Petroleum News. Alaska's bid to run its own Class VI carbon storage permits went to a public hearing at 10 a.m. on May 14th, 2026 at the commission's Anchorage offices, and written and oral comment closed at the conclusion of that hearing. If the Environmental Protection Agency grants primacy, the Alaska Oil and Gas Conservation Commission would regulate the underground injection control program for every Class VI well in the state. No decision has been published and no decision date has been set, which is now four months after the hearing.

Decided

20
INDIRECT LEGISLATION Closed

The AKLNG gas line tax bill

DECIDES · ALASKA LEGISLATURE, THIRD SPECIAL SESSION

A conference committee compromise unveiled July 2nd would swap the state property tax on the Glenfarne-led Alaska LNG project for a volumetric tax after five years of operation or 500 MMcf per day, and extend the completion deadline to the end of 2034. The House deadlocked 19 to 19 on July 16th over an expanded S corporation income tax, the governor rejected that provision, and a third special session convened July 27th with no bill from the governor and almost no legislators in the room.

Legislators decide; constituents reach them directly. The gas line would feed the grid most Alaska compute would ride on.
JUL 2Draft compromise unveiled
JUL 16Tentative House and Senate floor votes
JUL 19Special session ends
JUL 27Third special session convenes, 10:00 a.m.
AUG 10Senate could convene in full if the House passes a bill
AUG 12House Bipartisan Majority Caucus says HB 4001 lacks the votes to pass
AUG 13Governor says there is little reason to keep the third special session going
AUG 19Glenfarne says it is evaluating alternative paths after the tax effort fails
AUG 20Joint Senate and House Resources Committee meeting in Anchorage on Cook Inlet energy
AUG 25Third special session scheduled to end
2026-08-26 · It ended. The third special session ran out at midnight on Tuesday, August 25th, 2026 and lawmakers never took up HB 4001 in committee. Both chambers cancelled the pro forma sessions scheduled for that morning and the Capitol stayed empty. Governor Dunleavy said legislative leadership, particularly in the state Senate, had one job, to advance a clean Alaska LNG bill or load it down with an S corporation tax that killed it, and that they chose the latter. The three consecutive special sessions cost about $750,000, about $434,000 and about $76,000, more than $1 million together. A tax break for the project now waits on a new governor and a new Legislature after the November election, which puts it in 2027 at the earliest.
21
INDIRECT LEGISLATION Decided

Anchorage data-center zoning ordinance AO 2026-27

DECIDES · ANCHORAGE ASSEMBLY

On March 27th, 2026 the Anchorage Assembly adopted ordinance AO 2026-27 in a 10 to 2 vote, defining data centers in the municipal zoning code for the first time. It confines them to commercial and industrial zones, requires landscaping buffers and enclosed power equipment, and requires written statements from electric and water utilities that the grid has sufficient system capacity before a project proceeds. Members Scott Myers and Keith McCormick voted against it.

The elected Anchorage Assembly adopted the ordinance in a public 10 to 2 vote. Residents reach it through Assembly elections and public testimony.
MAR 27Assembly adopts AO 2026-27 (10 to 2)
2026-08-19 · Checked and unchanged. AO 2026-27 stands as adopted on March 27th, 2026 by a 10 to 2 vote, amending Title 21 to create a data center land use category, subject those facilities to conditional use review and use-specific performance standards, and require utility statements on system capacity before a project proceeds. It remains the only enacted local framework of its kind in Alaska. The ordinance also directs further regulatory work on energy-intensive uses, so the framework is expected to keep developing.
22
CLOSED LEGISLATION Closed

HB 259, state utility standards for large data centers

DECIDES · ALASKA LEGISLATURE (HOUSE ENERGY COMMITTEE)

HB 259, introduced by Rep. Donna Mears in January 2026, would have set utility rate-setting guidelines and community benefit agreement standards for large energy use facilities such as data centers, and given the Regulatory Commission of Alaska new duties over them. The House Energy Committee heard it twice, on January 29th and February 3rd, 2026, taking testimony from Greensparc, GCI, the Alaska Municipal League and former Rep. Paul Seaton. It never advanced out of that committee, and it carried a second referral to House Community and Regional Affairs it never reached. The bill died with the 34th Legislature at sine die on May 20th, 2026. Alaska still has no statewide cost-allocation rule governing how a large data-center load is billed against other ratepayers, which leaves that question with the Regulatory Commission of Alaska and with individual utility boards.

The bill died when the Legislature adjourned. No public path remains to this vehicle. A constituent who wants these standards has to ask a legislator to introduce them again in the 35th Legislature, which convenes in January 2027.
JAN 20Prefile released, read the first time, referred to House Energy then Community and Regional Affairs
JAN 29First House Energy Committee hearing
FEB 3Second House Energy Committee hearing, last recorded action on the bill
MAY 2034th Legislature adjourns sine die, the bill dies in committee
2026-09-11 · Checked against the Legislature's own record for HB 259, which still carries the bill in the House Energy Committee with the referral of January 20th, 2026 as its last recorded status. That matches what this entry says. The bill died in that committee when the 34th Legislature adjourned sine die on May 20th, 2026. Alaska still has no statewide rule on how a large data center load is billed against other ratepayers.
23
CLOSED PROCUREMENT Decided

The Army's Janus microreactor program at Fort Wainwright

DECIDES · DEPARTMENT OF THE ARMY, RUNNING ITS SOLICITATION THROUGH THE DEFENSE INNOVATION UNIT

Fort Wainwright was one of nine Army posts short listed for a microreactor under the Janus program. On August 26th, 2026 the Army named the first five installations and their vendors, and Fort Wainwright was not among them.

Industry submissions were taken through the Defense Innovation Unit and are evaluated privately. No public comment period exists at this stage, and no vendor has been named for Fort Wainwright.
NOV 18 2025Army solicitation released through the Defense Innovation Unit
DEC 15 2025Industry submissions due
AUG 26Army names its first five Janus installations and vendors; Fort Wainwright is not selected
2026-08-30 · Decided, and Fort Wainwright is not in it. The Army named its first five Janus installations on August 26th, 2026, Fort Bragg with Antares Nuclear, Fort Campbell with BWXT Advanced Technologies, Fort Hood with General Atomics Electromagnetic Systems, Fort Benning with Radiant Industries and Fort Drum with Westinghouse Government Services, against roughly $2.2 billion running across fiscal years 2027 through 2031 on milestone based payments. Fort Wainwright was short listed and not chosen, alongside Holston Army Ammunition Plant, Joint Base Lewis-McChord and Redstone Arsenal. The program itself continues, so a later round could still reach Alaska, and nothing published says it will.
24
INDIRECT UTILITY DECISION Closed

Copper Valley Electric's shelved nuclear reactor study

DECIDES · COPPER VALLEY ELECTRIC ASSOCIATION BOARD

Copper Valley Electric studied putting a 10 megawatt micro modular reactor into its isolated Glennallen and Valdez system, which is connected to no other utility and burns liquid fossil fuel for roughly a third of its power. The cooperative finished a pre feasibility study, published it, and then tabled the project indefinitely.

Copper Valley Electric is a member owned cooperative, so its board answers to ratepayers who elect it. The project is tabled, so there is nothing before the board to comment on now.
FEB 2 2022Study announced with Ultra Safe Nuclear Corporation
AUG 9 2023Board tables the project indefinitely
2026-09-06 · Checked and unchanged. The cooperative's project page still carries the August 9th, 2023 release headed that the micro modular nuclear reactor project was tabled indefinitely, with the completed pre feasibility study and the 2023 public meeting materials posted beside it. Nothing newer has been added.
25
CLOSED REGULATORY DOCKET next SEP 14

The Navy's permit for an under-ice robot navigation grid

DECIDES · NOAA NATIONAL MARINE FISHERIES SERVICE, OFFICE OF PROTECTED RESOURCES

NMFS has authorized the Office of Naval Research to harass marine mammals incidental to Year 9 of its Arctic Research Activities in the Beaufort and Chukchi seas, and what the authorization covers is an acoustic navigation grid. Up to six moored sources at 900 to 950 Hz and two drifting ice gateway buoys will transmit a 30 second pulse every four hours for one year, so that gliders operating under sea ice can fix a position by trilateration from those sources rather than by dead reckoning. The study area is about 639,237 square kilometres across the US Exclusive Economic Zone, the high seas north of Alaska and part of the Canadian Exclusive Economic Zone, coming within 204 kilometres of the Alaska coast at its nearest point. A research cruise of 22 days is planned to begin September 22nd, 2026 aboard R/V Sikuliaq, US Coast Guard Cutter HEALY or another vessel, while the sound sources stay in the water for twelve months. The authorization covers Level B harassment only and states that take by Level A harassment is neither anticipated nor authorized.

The record on this one is shut. NMFS took comment for 30 days after publishing the proposed authorization on July 22nd, 2026 and received three comment letters, all from private citizens, then issued the authorization on September 10th, 2026. There is no open filing path now. The next door is the Year 10 renewal, which the Year 9 proposal already invited comment on inside its own action line, and no renewal notice has published. Anyone who wants standing in Year 10 should watch the Federal Register for a proposed authorization under docket RTID 0648-XF889 or its successor.
JUL 22Proposed authorization published at 91 FR 46055, opening a 30 day comment period
SEP 4Authorization signed by the Director of the NMFS Office of Protected Resources
SEP 10Authorization issued and published at 91 FR 57547
SEP 14Authorization takes effect
SEP 22First research cruise planned to begin, 22 days in September and October
SEP 13 2027Authorization expires, one year being the statutory maximum
2026-09-12 · Location dropped the same day it was added, and the record says so rather than quietly losing a field. The item shipped with an exact point, 72.0 north and 150.0 west, standing in for a study area of about 639,237 square kilometres across the Beaufort and eastern Chukchi seas, the high seas and part of Canada's exclusive economic zone. No claim in the run's verified set establishes those coordinates, and the site publishes a location as schema.org GeoCoordinates and as a pin on the docket map, so a representative point was being published as a measured fact. The area itself is in this item's summary and in the deck, where it belongs. The validator's own remedy text is the one taken here, that an item keeps its page and its row without claiming a spot on the map.

Deadline alerts, in your inbox

One email when a public comment window opens or a decision is about to land. Nothing else, ever. Unsubscribe any time.

All sources verified against claims. The data behind this page is public at docket.json.

Alaska AI keeps this docket current with the same kind of autonomous system it builds for Alaska businesses.